Service Manual
Table Of Contents
- Safety Notices
- Definitions
- General Information
- Installation
- Stacking Two Ice Machines on a Single Storage Bin
- Location of Ice Machine
- Clearance Requirements
- Dual Evaporator Model Installation on a Manitowoc Bin
- Ice Machine on a Dispenser Installation
- Water Supply and Drains
- Lineset Applications
- QuietQube® Remote Condensing Unit
- Additional Refrigerant Charge For 51' to 100' Line Sets
- Maintenance
- Operation
- Menu Navigation
- Component Check Procedures
- Control Board, Display And Touchscreen
- Operating an ice machine without a Touchscreen
- Control Board Relay Test
- Programming A Replacement Control Board
- USB Flash Drive Specifications and Formatting
- Exporting Data to a Flash Drive
- Upgrading Firmware with a Flash Drive
- Main Fuse
- Bin Switch
- Water Level Control Circuitry
- Ice Thickness Probe (Initiates Harvest)
- Bin Level Probe
- Thermistors
- High Pressure Cutout (HPCO) Control
- Low Pressure Cutout (LPCO) Control
- Compressor Time Delay
- Fan Cycle Control
- Harvest Assist Air Pump
- Compressor Electrical Diagnostics
- Diagnosing Start Components
- Refrigeration Components
- Recovery/Evacuation/Charging Procedures QuietQube® Models
- System Contamination Clean-Up
- Total System Refrigerant Charge QuietQube® CVD Models
- Control Board, Display And Touchscreen
- Charts
- Diagrams
Part Number: 000015431 Rev 02 6/20 147
Ice Thickness Probe Diagnostics
1. Perform Control Board Self Check and insure the
internal ITP circuit passes before proceeding.
(Menu/Service/Diagnostics/Control Board/Self Check)
• Ice Thickness Circuit: Pass = Continue with step #2.
• Ice Thickness Circuit: Fail = Change control board.
2. Remove all ice from the evaporator when present, by
initiating a manual harvest in the service menu.
3. Press the power button and turn off the ice machine.
4. Disconnect power to the ice machine at the main
disconnect.
5. Inspect the ice thickness probe for physical damage.
On the face of the probe look for bulging, cracks
around the nipple and deformed pivot pins or pivot
pin arms.
6. Verify the ice thickness probe gap is approximately
9/32" (7 mm) and the ice thickness probe wire and
bracket do not restrict movement of the probe. See
“Ice Thickness Probe (Initiates Harvest)” on page
145.
7. Reapply power to the ice machine at the main
disconnect and confirm the ice machine is off.
8. Navigate to Real Time data (Menu/Service/Data/
Real Time data/Inputs) and observe ITP FFT 100 Hz &
120 Hz.
9. Observe the initial number range and perform a tap
test.
• Remove the water curtain or splash shield if present.
• Lift the ice thickness probe and carefully tap the nipple
on the face of the probe for at least 10 seconds.
NOTE: When performing tap test:
• Pass = ITP is not the problem
• Fail = Check DC Voltage on the control board