S Model QuietQube® Ice Machines with CVD® Technology Installation Training
Overview ³ Compressor, Condenser, Accumulator and HPCV are Outside ³ Line Set is: ³ High Pressure Liquid Line ³ Low Pressure Suction Line ³ Evaporator, Receiver and Harvest Valve in Head Section No Interconnecting Control Wiring!
Typical QuietQube System Installation
Model Numbers This training covers the following models: Ice Machine Head Section CVD Condensing Unit SD0672C SY0674C CVD0675 SD0872C SY0874C CVD0885 SD1072C SY1074C CVD1085 SD1272C SY1274C CVD1285 SD1472C SY1474C CVD1485 SD1872C SY1874C CVD1885 SD2072C SY2074C CVD2075
Important Information Prior to Installation ³ Read Installation, Use & Care Manual S Model QuietQube ice machines cannot be stacked. Failure to follow installation guidelines may affect warranty coverage. Manitowoc remote systems are only approved and warranted as a complete new package. Warranty on the refrigeration system will be void if a new ice machine head section is connected to pre-existing (used) tubing or condensing units or vice versa.
Verify Components Next verify that you have all the correct components for the ice machine that is being installed ³Bin ³Adapters ³Kits ³Location
Installation Requirements The location selected for the ice machine must meet the following criteria. If any of these criteria are not met, select another location. ³Must have open site (gravity) drain available (see Water Supply and Drain Requirements). ³Must have a grounded, polarized electrical power supply on a dedicated electrical circuit (only appliance on circuit). If GFCI (ground fault circuit interrupter) is required by your local electrical code, it must be breaker type, not outlet type.
Head Section ³ The air temperature must be at least 35°F (1.6°C), but must not exceed 110°F (43.4°C). ³ The location must be free of airborne and other contaminants. ³ The location must not be near heat-generating equipment or in direct sunlight. ³ The location must not obstruct airflow through or around the ice machine. Clearances Top 5” (12.7 cm) is recommended for efficient operation and removal of top cover/servicing. Sides 5” (12.7 cm) is recommended for efficient operation and servicing.
Location of Condensing Unit ³ The air temperature must be at least -20°F (-28.9°C) but must not exceed 130°F (54.4°C). ³ CVD675/CVD1185/CVD2075 Only - The air temperature must be at least -20°F (-28.9°C) but must not exceed 120°F (48.9°C). ³ CVD1486 Only- The air temperature must be at least 50°F (10°C) but must not exceed 110°F (43°C). ³ The location must not allow exhaust fan heat and/or grease to enter the condenser. ³ The location must not obstruct airflow through or around the condensing unit.
Condensing Unit Clearances CVD675/CVD885/CVD1085/CVD1185/CVD2075 Top/Sides There is no minimum clearance required, although 6” (15.2 cm) is recommended for efficient operation and servicing only. Front/Back 48” (122 cm) CVD1285/CVD1485/CVD1885 Top/Sides There is no minimum clearance required, although 6” (15.2 cm) is recommended for efficient operation and servicing only. Front 24” (61 cm) Back 48” (122 cm) CVD1486 ONLY Top - 5” (12.7 cm) is required for efficient operation and servicing.
CVD Rise & Drop Verify the Condensing Unit and Ice Machine Head Section are within the guidelines
Electrical Service Requirements ³ All electrical work, including wire routing and grounding, must conform to local, state and national electrical codes. The following precautions must be observed: The ice machine must be grounded. ³ A separate fuse/circuit breaker must be provided for each condensing unit. ³ A qualified electrician must determine proper wire size dependent upon location, materials used and length of run (minimum circuit ampacity can be used to help select the wire size).
Head Section Electrical Total Amps **Minimum Wire Size Required by Manitowoc Minimum Breaker Size Required by Manitowoc Ice Machine Voltage Phase Cycle Maximum Fuse/Circuit Breaker S0600C 115/1/60 230/1/50 15 amp 15 amp 1.1 0.6 #14 Solid Copper Conductor 15 amp 15 amp S0850C 115/1/60 230/1/50 15 amp 15 amp 1.1 1.5 #14 Solid Copper Conductor 15 amp 15 amp IB0620C IB0820C IB1020C 115/1/60 230/1/50 15 amp 15 amp 1.4 0.
CVD Electrical Condensing Unit Voltage/Phase/Cycle Maximum Fuse/ Circuit Breaker Minimum Circuit Amps **Minimum Wire Size Required by Manitowoc Minimum Breaker Size Required by Manitowoc CVD0675 208-230/1/60 208-230/3/60 230/1/50 15 amp 15 amp 15 amp 9.6 7.3 9.0 #14 Solid Copper Conductor #14 Solid Copper Conductor #14 Solid Copper Conductor 15 amp 15 amp 15 amp CVD0885 208-230/1/60 208-230/3/60 230/1/50 20 amp 15 amp 20 amp 11.8 9.1 10.
Verify Head Section Always verify that you have received the correct ice machine & condensing unit prior to installing Model Number on Box
Inspection ³Remove carton & inspect ice machine and condensing unit for shipping damage
Remove all Panels Single Evaporator - Hinged Front Door Removal ³ ³ ³ ³ ³ ³ Loosen Screws on the left and right front panels Open the left front door 45 degrees and support with hand Depress the top pin to disengage door, tilt forward Lift off of bottom pin The right front panel lifts up to disengage Remove the top cover and the remaining panels
Remove all Panels Dual Evaporator - Front Panel Removal ³ Loosen Screws on the front panel ³ The entire front panel lifts up to disengage ³ Remove the top cover and the remaining panels
Model/Serial Number Location Back of Ice Machine Inside of Ice Machine
Example Data Plate Model Number Serial Number – NO Date code in new serial numbers Refrigerant Voltage Manufactured Date
Warranty Registration Warranty Registration Form Website
Level Bin ³Thread leveling leg into base of bin ³Level the bin to assure the bin door closes and seals properly
Mount on Bin ³Place the ice machine on top of the bin. ³Make sure ice machine is flush with the sides of the bin.
Ice Machine Wiring ³Install strain relief and proper wiring to ice machine head section
Water Connections Location Water Temperature Water Pressure Ice Machine Fitting Tubing Size Up to Ice Machine Fitting Ice Making Water Inlet 35°F (1.6°C) Min. 90°F (32.2°C) Max. 20 psi (1.4 bar) Min. 80 psi (5.5 bar) Max. 3/8” Female Pipe Thread 3/8” (9.5 mm) min. inside diameter Water Cooled Condenser 35°F (1.6°C) Min. 90°F (32.2°C) Max 20 psi (1.4 bar) Min. 150 psi (10.3 bar) Max. High Pressure Option 20 psi (1.4 bar) Min. 350 psi (24.1 bar) Max. 1/2” Female Pipe Thread 1/2” (12.7 mm) min.
Water Supply ³Do not connect the ice machine to a hot water supply. ³If water pressure exceeds the maximum recommended pressure (80 psi), obtain a water pressure regulator from your Manitowoc distributor.
Water Fittings ³ Do not apply heat (torch) to the Water Inlet Fitting or Drain Fitting ³ Solder Water Connection before installing on ice machine ³ Water fittings have plastic and will melt when heated ³ Union must be installed to allow removal of ice machine
Potable Water Supply ³Installation with Water Filter ³ Install union, additional shut-off is not required ³ Copper or plastic tubing may be used ³ Refer to Arctic Pure Install Use and Care manual for complete installation instructions
Potable Water Supply ³Water Installation without filter ³Install union and shut-off valve
Head Section Drains ³ Install 18” Vent Tubes ³Ice Machine & Bin drains must be run separately ³ Drains Must: ³Be run separately ³Have a minimum pitch of 1.
Roof Penetration Verify Ice Machine and CVD® Condensing Unit Locations Are Within Guidelines. ³ Prior to installation of the ice machine head section and CVD® condensing unit be sure that the distance between then is within the line set routing guidelines. Roof/Wall Penetration ³ If required, cut a 3-inch (76.2 mm) circular hole in the wall or roof for routing of refrigeration tubing. A qualified person must perform all roof penetrations.
Lift Unit ³Trained & qualified personnel are required for rigging and lifting
Curb & Pitch Pockets ³ The type of curbs and pitch pockets are dependant on the roofing material. ³ Contact a roofing company to install the curb & pitch pockets.
Place Units ³ Place condensing units on curb and secure ³ An electrician will determine wire size & install disconnect for each condensing unit
Refrigeration System Installation ³ The ice machine head section contains refrigerant charge. The ice machine head section contains 3 refrigeration valves that must remain closed until proper installation of the line sets is completed. ³ Disconnect electrical power to the ice machine head section and CVD® condensing unit before proceeding.
CVD Line Sets QuietQube® Ice Machine Remote Single Circuit Condenser S0600C IB620C CVD675 S0850C IB820C CVD885 S1000C CVD1085 IB1020C CVD1185 S1200C CVD1285 S1470C CVD1485 CVD1486 S1870C CVD1885 S2070C CVD2075 Line Set* RC-21 RC-31 RC-51 RC-20 RC-30 RC-50 *Line Set Suction Line Liquid Line Insulation Thickness RC 21/31/51 5/8 inch (15.9 mm) 3/8 inch (9.5 mm) 1/2”(13mm) Suction Line 1/4” (7mm) Liquid Line RC 20/30/50** 3/4 inch (19.1 mm) 1/2 inch (12.
Line Set Length, Rise & Drop LINE SET LENGTH 100 feet (30.5 m) Length: The maximum measured length the line set can be. The receiver is designed to hold a charge sufficient to operate the ice machine in ambient temperatures between 20°F (-28.9°C) and 130°F (54.4°C)*, with line set lengths of up to 100 feet (30.5 m).
Suction Line Oil Traps 0 to 20 feet (0 to 6.1 m) Rise: The ice machine head section has one oil trap built in which allows for a maximum condenser rise of 20 feet (6.1 m) without additional traps in the suction line. 21 to 35 feet (6.4 to 10.7 m) Rise: The suction line requires an additional Oil Trap (“S” type) to be installed. Install the trap as close as possible to midpoint between the ice machine head section and CVD condensing unit. See chart below for kits.
Line Set Installation ³ Route refrigeration tubing ³ The maximum measured length the line set can be is 100’ (30.5 m) (no exceptions) ³ The maximum amount of line set which can be exposed on the rooftop is 25% of the total length of the line set.
Suction Line Oil Traps 0 to 20 feet (0 to 6.1 m) Rise: The ice machine head section has one oil trap built in which allows for a maximum condenser rise of 20 feet (6.1 m) without additional traps in the suction line. 21 to 35 feet (6.4 to 10.7 m) Rise: The suction line requires an additional Oil Trap (“S” type) to be installed. Install the trap as close as possible to midpoint between the ice machine head section and CVD condensing unit.
Secure Line Set ³ Secure Line Set as Needed ³ Do not crush/compress insulation
Connect the Line Set Ice Machine The line set can be routed for entry through the top or rear of the ice machine head section. ³ Top routing requires the cover to be trimmed. ³ Rear routing may require the use 90° elbows on some models. The line set shut off valves at the back of the ice machine must remain closed and be protected from heat during the brazing process. Wrap the valves in a wet rag or other type of heat sink prior to brazing.
Connect the Line Set Condensing Unit ³ The condensing unit ships from the factory pressurized with a 50/50 mixture of nitrogen/helium. Bleed off pressure from both suction and liquid line access ports prior to cutting into refrigeration lines. ³ The compressor oil rapidly absorbs moisture. Be prepared to complete line set installation and start your evacuation process in order to minimize the time the compressor is exposed to the atmosphere.
Pressure Test & Evacuate Leave the line set shut off valves closed (front seated). Pressure test the line sets and CVD condensing unit with 150 psig of dry nitrogen. Add nitrogen at the line set shut off valves located at the back of the ice machine. Complete the pressure test, verify no leaks are present and remove the nitrogen from the system before connecting the vacuum pump. Connect a vacuum pump to both of the line set shut off valves located at the back of the ice machine head section.
Open the Valves Prior to Starting Open The Valves Prior To Starting The Ice Machine. A. Slowly backseat (open-turn counterclockwise) the suction line shut off valve. B. Slowly backseat (open-turn counterclockwise) the liquid line shut off valve. C. Slowly backseat (open-turn counterclockwise) the receiver service valve. NOTE: You will not hear refrigerant flow when the valves are opened. Refrigerant will not flow until the toggle switch is placed in the ice position and the solenoid valve opens.
Leak Check the System ³ Leak check the new line set connections at the ice machine head section, condensing unit and S trap as well as all factory joints throughout the entire system. ³ Disconnect power to the CVD condensing unit. Place the ICE/OFF/CLEAN toggle switch into the ICE position. This allows the low side and high side pressures to equalize. ³ Place the ICE/OFF/CLEAN toggle switch in the OFF position. Connect power to the CVD condensing unit and allow system to pump down.
Insulation Requirements The following insulation requirements prevent condensation at 90°F (32.2°C) ambient 90% Relative Humidity. If higher humidity is expected, increase insulation thickness. Suction Line Liquid Line 3/4 inch (19.1 mm) 1/2 inch (12.7 mm) 5/8 inch (15.9 mm) 3/8 inch (9.5 mm) 7/8 inch (22.2 mm) 5/8 inch (15.9 mm) Min.
Refrigerant Charge The ice machine is pre-charged with refrigerant. Additional refrigerant may be required on some models, when the line set length is between 50’ - 100’.
Final Set-Up
Installation Checklist ³Complete the installation checklist in the Installation, Use & Care Manual
Complete Installation ³Sanitize the Ice Machine ³Energize ³Verify Water Level ³Run 2 Freeze Cycles
S Model QuietQube® Ice Machines with CVD® Technology Installation Quiz Click Here to Launch