User manual
DEFINITY ECS Release 8.2 Maintenance for R8.2csi 
555-233-119  Issue 1
April 2000
 Maintenance Objects
3-860OPS-LINE (DS1 OPS Line) 
3
Audit and Update Test (#36)
This test sends port level translation data from switch processor to the DS1 
Interface circuit pack to assure that the trunk’s translation is correct. Translation 
updates include the following data: trunk type (in/out), dial type, timing 
parameters, and signaling bits enabled. The port audit operation verifies the 
consistency of the current state of the trunk as kept in the DS1 Interface circuit 
pack and in the switch software.
PASS The port can correctly conference multiple connections. User-reported 
troubles on this port should be investigated using other port tests and 
by examining station, trunk, or external wiring.
0NO 
BOARD
The test could not relate the internal ID to the port (no board). This 
could be due to incorrect translations, no board is inserted, an incorrect 
board is inserted, or an insane board is inserted.
1. Check to ensure that the board translations are correct. Use the list 
config command, and resolve any problems that are found.
2. If the board was found to be correctly inserted in step 1, issue the 
busyout board command.
3. Issue the reset board command.
4. Issue the release busy board command.
5. Issue the test board long command. This should re-establish the 
linkage between the internal ID and the port. If this is not the case, 
dispatch to check to ensure that there is a valid board inserted.
Table 3-372. TEST #7 Conference Circuit Test — Continued
Error 
Code
Test 
Result Description/ Recommendation
Continued on next page