Installation guide
Chapter 2. CLI Syntax Reference
80 3ware SATA+SAS RAID Controller Card CLI Guide, Version 10.2
When you issue this command, the specified rebuild begins if the rebuild 
schedule is disabled; otherwise, the rebuild pauses until the next scheduled 
rebuild. A file system check is recommended following rebuild when using 
the ignoreECC option.
/cx/ux start verify
Also referred to as a manual verify, the /cx/ux start verify command starts a 
background verification process on the specified unit /cx/ux. 
When you issue this command, the specified unit begins verification if the 
verify schedule is basic or disabled; otherwise it pauses until the next 
scheduled verify timeslot on the advanced schedule.
If verify=basic or is disabled, verification of the specified unit begins 
immediately. If verify=advanced, the verify pauses until the next timeslot on 
the advanced schedule. For more information, see “/cx set 
verify=advanced|basic|1..5” on page 66.
The following table summarizes how manual verify works.
Verify pauses if a rebuild, migration, or initialization is in progress and 
resumes after those operations are completed.
/cx/ux stop verify
The /cx/ux stop verify command stops a background verification process on 
the specified unit /cx/ux. 
/cx/ux flush
The /cx/ux flush command allows you to flush the write cache on the 
specified unit /ux associated with controller /cx. Note that this command does 
not apply to spare unit types. 
Table 7: Manual Verify Behavior (/cx/ux start verify)
Command Setting Action
Basic Verify Schedule 
(verify=basic)
Runs immediately
Advanced Verify Schedule 
(verify=advanced)
Follows Advanced Verify Schedule