Installation Guide

10
APPENDIX Framing a Rough Opening Parallel To Ceiling Joist
1
Make a rough opening to the size as required in table 1 ensuring that the dimensions of
2
the diagonals of the frame are the same as illustrated in Figure 17.
3
4
MODEL
ROUGH
OPENING
CEILING HT.
RANGE
A
LANDING
SPACE
B
SWING
CLEARANCE
C
AA2510R5
25 1/2” x 54
78 10 3
* 66
74
AA2210R5
22 1/2” x 54
78 10 3
* 66
74
WA2210L
22 1/2” x 54
7’ 9” 10’ 3”
* 65
74
* FOR 13 CEILING HEIGHT
5
TABLE 1 (repeated from page 3)
6
7
8
9
A.
For Rough opening without joist removal (Figure 17)
10
Locate headers in front and rear of the
11
opening as shown in Figure 17.
12
Check for squareness by making sure
13
that diagonal measurements are
14
within 1/8.
15
Secure using (3) 16d nails into each end
16
of the Header.
17
18
19
20
21
22
FIGURE 17
23
24
B.
Rough opening with joist removal (Figure 18)
25
Install temporary support boards
26
spanning both sides of joists to be
27
removed.
28
Remove joist at length to allow for
29
double headers to be installed on both
30
ends of opening.
31
32
Continued on next page...
33
34
35
36
37
FIGURE 18
38
Diagonal