Install Instructions
6
2 Pre-installation
SDT/SET Installation & Operation Manual
Failure to properly support the tank could
result in property damage or personal injury.
WARNING
4. The tank may be located some distance from the boiler
provided the pump is designed to provide the flow called
for in Table 3B (page 8)- Pressure Drop Values, through the
coil. The further the tank is from the boiler, the longer the
response of the boiler will be to a call from the tank zone.
Insulate piping between the boiler and the tank.
Recommended Clearances
The installation location must provide adequate clearances for
servicing and proper operation of the water heater. A 12 inch
vertical clearance is recommended from the top of the water
heater. A zero clearance is allowed for the sides of the water
heater. However, boiler, electrical, and servicing clearances
must be figured when locating the water heater.
Minimum Clearance to the Element Cover
See FIG 2-1. Clearances must be a minimum of 24 inches to
allow for element removal and replacement on SET model.