APPLICATIONS INFORMATION
3. Do the LTC3827 V
FB
pins’ resistive dividers connect to
the (+) terminals of C
OUT
? The resistive divider must be
connected between the (+) terminal of C
OUT
and signal
ground. The feedback resistor connections should not
be along the high current input feeds from the input
capacitor(s).
4. Are the SENSE
–
and SENSE
+
leads routed together
with minimum PC trace spacing? The fi lter capacitor
between SENSE
+
and SENSE
–
should be as close as
possible to the IC. Ensure accurate current sensing with
Kelvin connections at the SENSE resistor.
5. Is the INTV
CC
decoupling capacitor connected close to
the IC, between
the INTV
CC
and the power ground pins?
This capacitor carries the MOSFET drivers current peaks.
An additional 1µF ceramic capacitor placed immediately
next to the INTV
CC
and PGND pins can help improve
noise performance substantially.
6. Keep the switching nodes (SW1, SW2), top gate nodes
(TG1, TG2), and boost nodes (BOOST1, BOOST2) away
from sensitive small-signal nodes, especially from
the opposites channel’s voltage and current sensing
feedback pins. All of these nodes have very large and
fast moving signals and therefore should be kept on
the “output side” of the LTC3827 and occupy minimum
PC trace area.
7. Use a modifi ed “star ground” technique: a low imped-
ance, large copper area central grounding point on
the same side of the PC board as the input and output
capacitors with tie-ins for the bottom of the INTV
CC
decoupling capacitor, the bottom of the voltage feedback
resistive divider and the SGND pin of the IC.
PC Board Layout Debugging
Start with one controller on at a time. It is helpful to use
a DC-50MHz current probe to monitor the current in the
inductor while testing the circuit. Monitor the output
switching node (SW pin) to synchronize the oscilloscope
to the internal oscillator and probe the actual output voltage
as well. Check for proper performance over the operating
voltage and current range expected in the application. The
frequency of operation should be maintained over the input
voltage range down to dropout and until the output load
drops below the low current operation threshold—typi-
cally 10% of the maximum designed current level in Burst
Mode operation.
The duty cycle percentage should be maintained from cycle
to cycle in a well-designed, low noise PCB implementation.
Variation in the duty cycle at a subharmonic rate can sug-
gest noise pickup at the current or voltage sensing inputs
or inadequate loop compensation. Overcompensation of
the loop can be used to tame a poor PC layout if regula-
tor bandwidth optimization is not required. Only after
each controller is checked for its individual performance
should both controllers be turned on at the same time.
A particularly diffi cult region of operation is when one
controller channel is nearing its current comparator trip
point when the other channel is turning on its top MOSFET.
This occurs around 50% duty cycle on either channel due
to the phasing of the internal clocks and may cause minor
duty cycle jitter.
Reduce V
IN
from its nominal level to verify operation
of the regulator in dropout. Check the operation of the
undervoltage lockout circuit by further lowering V
IN
while
monitoring the outputs to verify operation.