ENGLISH ITALIANO ESPAÑOL FRANÇAIS INSTALLATION MANUAL DEUTSCH AIR CONDITIONER ΕΛΛΗΝΙΚΆ ČEŠTINA For more information, Refer to the CD or LG Web site (www.lg.com). www.lg.com P/NO : MFL67855509 LIMBA ROMÂNĂ [Representative] LG Electronics Inc. EU Representative : LG Electronics European Shared Service Center B.V. Krijgsman 1, 1186 DM Amstelveen, The Netherlands [Manufacturer] LG Electronics Inc.
Ventilator Installation Manual TABLE OF CONTENTS Installation Requirements Safety Precaution.................3 Introduction ..........................8 Feature Dimension Diagram...............................8 Standard drawing of installation ........................................9 Installation ..........................11 Selection of the best location ..............................11 Ceiling dimension and hanging bolt location .................12 Indoor Unit Installation.......
Safety Precautions To prevent injury to the user or other people and property damage, the following instructions must be followed. n Incorrect operation due to ignoring instruction will cause harm or damage. The seriousness is classified by the following indications. CAUTION This symbol indicates the possibility of injury or damage. WARNING n Installation For electrical work, contact the dealer, seller, a qualified electrician, or an Authorized Service Center. Always ground the product.
Safety Precautions For installation, always contact the dealer or an Authorized Service Center. • There is risk of fire, electric shock, explosion, or injury. For re-installation of the installed product, always contact the dealer or an Authorized Service Center. Do not install the product on a defective installation stand. Do not let the product run for a long time when the humidity is very high and a door or a window is left open. • It may cause injury, accident, or damage to the product.
Safety Precautions Use the designated electrical wires for the terminal board connections, and connect the wires securely so that they will not become disconnected. (Failure to ensure proper connections may cause fire.) When passing metal ducts through wooden buildings clad with metal laths, wire laths or metal, these ducts must be installed in such a way that they will not make electrical contact with the metal laths, wire laths or metal sheets.
Safety Precautions Be cautious that water could not enter the product. Turn the breaker off when cleaning or maintaining the product. • There is risk of fire, electric shock, or product damage. • There is risk of electric shock. The outside ducts must be tilted at a gradient (1/30 or more) down toward the outdoor area from the ventilator unit, and properly insulated. (The entry of rain water may cause power leaks, fire or damage to household property.
Safety Precautions • To avoid vibration or water leakage. Use two or more people to lift and transport the product. • Avoid personal injury. Do not install the product where it will be exposed to sea wind (salt spray) directly. • It may cause corrosion on the product. Corrosion, particularly on the condenser and evaporator fins, could cause product malfunction or inefficient operation. Do not install the ventilation unit alone for controlling room temperature.
Introduction Introduction Feature Dimension Diagram Model : LZ-H050GXN0, LZ-H080GXN0, LZ-H100GXN0 LZ-H050GXH0, LZ-H080GXH0, LZ-H100GXH0 Application tools (CMH) Unit : mm Pipe ConnecPitch of Suspension Duct Connection Duct Pitch tion Fixture Flange Figure Model A B C D E F G H J K L M N P Q Drain Hose Water Supply PipWeiWidth Connection ing Connection ght R S T U V kg 29 55 83 1239 105 LZ-H050GXN0/LZ-H050GXH0 LZ-H080GXN0/LZ-H080GXH0 1667 1140 365 599 1006 1204 185 242 252 74 510
Standard drawing of installation ENGLISH Standard drawing of installation LZ-H050GXN0 / LZ-H080GXN0 / LZ-H100GXN0 Air supply grille (user-supplied) Ceiling suspension bolts position Air return grille (user-supplied) A EA (Exaust air outlet) B OA Inspection hatch 600 ( Inspection hatch 600 Y duct connecting (user-supplied) 150~250 More than 600 (Fresh air outlet) 600 150~200 Maintenance space Total heat Excha nger Air Filter ) Ceiling Fixing Bolt (user-supplied) Duct normal diameter ØC(us
Standard drawing of installation LZ-H050GXH0 / LZ-H080GXH0 / LZ-H100GXH0 Air supply grille (user-supplied) Ceiling suspension bolts position Air return grille (user-supplied) A EA B (Exaust air outlet) OA Inspection hatch 600 ( Inspection hatch 150~200 600 Y duct connecting (user-supplied) 150~250 More than 600 (Fresh air outlet) 600 Maintenance space Total heat Excha nger Air Filter ) Cistern Tank Ceiling Fixing Bolt (user-supplied) Duct normal diameter ØC(user-supplied) Strainer (user-s
Installation ENGLISH Installation Read completely, then follow step by step. Selection of the best location Install the ventilator in the location that satisfies the following conditions. • The place shall easily bear a load exceeding four times the indoor unit’s weight. • The place shall be able to inspect the unit as the figure. • The place where the unit shall be leveled. • The place shall allow easy water drainage.(Suitable dimension “*C” is necessary to get a slope to drain as figure.
Installation Ceiling dimension and hanging bolt location n Installation of Unit Install the unit above the ceiling correctly. CASE 1 POSITION OF SUSPENSION BOLT • Apply a Flexible duct between the unit and duct to absorb unnecessary vibration. 1006 599 Return Air(RA) 1140 1204 Exhaust Air(EA) Supply Air(SA) Outdoor Air(OA) 600 600 Inspection hatches 600 600 CASE 2 • Install the unit leaning to a drainage hole side as a figure for easy water drainage.
Installation • Select and mark the position for fixing bolts. • Drill the hole for set anchor on the face of ceiling. • Insert the set anchor and washer onto the suspension bolts for locking the suspension bolts on the ceiling. • Mount the suspension bolts to the set anchor firmly. • Secure the installation plates onto the suspension bolts (adjust level roughly) using nuts, washers and spring washers.
Installation • Attach the hanger bracket to the suspension bolt. Be sure to fix it securely by using nuts and washers (locally procured) from the upper and lower sides of the hanger bracket. • Install the unit after checking the indoor (SA/RA) and outdoor (EA/OA) in accordance with the figure duct direction label. • Adjust the height of the unit. (Tighten the double nuts securely.) • Check the unit is horizontally level.
Drain Piping and Water Supply Work • Always lay the drain with downward inclination (1/100 to 1/50). Prevent any upward flow or reverse flow in any part. • 10mm or thicker formed thermal insulator shall always be provided for the drain pipe. Thermal insulator (Local supply) Drainage pipe (Local supply) Unit Drainage hole Make sure to be closed.
Drain Piping and Water Supply Work Check the drainage • Test the drainage by pouring 1000cc of water into the drain pan through the inspection hole by removing the maintenance cover (8 screws) or through the outlet duct joint of supply air to room (SA). • Make sure that heat insulation work is executed on the Indoor drain piping and Drain outlet to prevent any possibility water leakage due to dew condensation.
Drain Piping and Water Supply Work • After checking that the drain piping connections do no leakage, insulate them using the insulation. (Tighten with a clamp material) • Wrap the drain piping with insulation to prevent condensation from forming.
Duct Connection Duct Connection • After securely connect the duct with the duct connection flange, wrap it with a commercial aluminium tape so that air cannot be leaked. • Adjust the duct from the ceiling so that no force is applied to the main body of the ventilation system. • Always use two ducts at the outdoor with the heat insulating material for prevention of dewing.
Connecting Pipes ENGLISH Connecting Pipes Preparation of Piping Main cause of gas leakage is defect in flaring work. Carry out correct flaring work in the following procedure. Copper tube Slanted Uneven Rough 90° Cut the pipes and the cable. • Use the accessory piping kit or the pipes purchased locally. • Measure the distance between the indoor and the outdoor unit. • Cut the pipes a little longer than measured distance. • Cut the cable 1.5m longer than the pipe length.
Connecting Pipes Connecting the pipings to the indoor unit and drain hose to drain pipe • Align the center of the pipings and sufficiently tighten the flare nut by hand. • Tighten the flare nut with a wrench. Outside diameter mm Ø6.35 Ø9.52 Ø12.7 Ø15.88 Ø19.05 Indoor unit tubing Torque kg.m inch 1/4 3/8 1/2 5/8 3/4 1.8~2.5 3.4~4.2 5.5~6.6 6.6~8.2 9.9~12.1 Flare nut Pipings Spanner (fixed) Flare nut Torque wrench • When extending the drain hose at the indoor unit, install the drain pipe.
Wiring Connection ENGLISH Wiring Connection Electrical Wiring Perform the electrical wiring work according to the electrical wiring connection. • All wiring must comply with local requirements. • Select a power source that is capable of supplying the current required by the ventilator. • Use a recognized ELCB(Electric Leakage Circuit Breaker) between the power source and the unit. A disconnection device to adequately disconnect all supply lines must be fitted.
Wiring Connection Connecting Cable Specification : The connecting cable, being used to connect the indoor unit and outdoor unit, should be complied with IEC 60335-1 standard (This equipment shall be provided with a cord set complying with the national regulation). If the supply cable is damaged, it must be replaced by a special cable or assembly available from the manufacturer or its service agent. GN /YL 20 mm WARNING Make sure that the screws of the terminal are free from looseness.
Wiring Connection • Pass the power supply wiring and the ground wiring through the wiring through-hole into the electrical parts box and secure with the included clamping material after connecting the wires to terminal blocks. Terminal Block 1 wiring Terminal Block 2 wiring 1(A)2( A) 3 4 Short-circuit wire Remove when installing the humidistat.
Wiring Connection Clamping of cables 1) Arrange 2 power cables on the control panel. 2) First, fasten the Plastic clamp with screw to the inner boss of control panel. Additional Parts Wiring Power Supply Wiring Main PCB Terminal Block 1 Clamp screw Clamp screw Motor Driver PCB Remote Controller Wiring Terminal Block 2 Sub PCB Clamp screw CAUTION • See “Label Circuit” on the backside of the cover of control box for electric wiring work.
Wiring Connection 1. Pass into the electric parts box together with the power wire through the power wiring through-hole. 2. Remove the short-circuit wires (3 and 4) on the TB 2 terminal block and connect the wiring for the humidity regulator. 3. Secure with cramping material together with the power wire. Wiring specifications Sheathed wire (should be complied with IEC60245 standard) Size 0.75 - 1.25 mm2 Length MAX.
Wiring Connection Wiring Example • This unit can be used as part of the combined operation system used together with indoor units (Multi-V system air conditioners), or as an independent system for processing outside air.
Field Setting and Test Run Perform field setting with the remote controller 1. Function Explanation - After installation by the installer, it performs the function for product setting. 2. Setting 1) function entry 1.1) Input the Function setting button for 3 seconds to enter the installer setting mode. 1.2) When entering, LCD other than relevant LCD is not appeared. ESP value Function code, ESP code Function setting button 2) Function operation 2.
Field Setting and Test Run Installer Setting Code and Value Table No. Function Code Available Product Value 1 Test run 01 DX 2 Setting Address of Central Control 02 General/DX 3 Supply ESP 03 4 Exhaust ESP 04 5 Product direction 05 General 6 Quick Refresh Priority 06 General/DX 01:Supply air first, 02:Exhaust air first 7 Master setting 07 General/DX 00:Slave, 01:Master 8 Override setting 08 DX 9 Dry Contact Auto 09 General/DX 00:OFF, 01:ON 10 Release of 3Min.
Field Setting and Test Run 1. Function explanation: Set the E.S.P(RPM) value of air conditioner indoor unit. 2. Function control and setting(refer to the explanation at prior page about function entry) 2.1) Select the wind strength with inputting up-down button. * 01:low, 02:high, 03:very high(Seg flickering) 2.2) Move the setting items with inputting the right-left button. * wind strength selection ↔ RPM value selection(seg of selected item is flickering) 2.
Field Setting and Test Run ■ Zone Stats 1. Function explanation: Set the wind strength option of indoor unit as Variable or fixed. 2. Function control and setting 2.1) Select the wind strength option value with inputting the up-down button. *01: Variable, 02: Fixed 2.2) Complete the setting with inputting Setting/Cancel button.(Send setting data to indoor unit) ※ when selecting wind strength as fixed, ESP is not changeable. ■ Selecting Celsius or Fahrenheit 1.
Field Setting and Test Run (1) Check that the water supply piping is connected securely. (2) Open the water supply shut-off valve. (No water will be supplied at this time.) (3) Run the eco-V unit in heating mode. (See the operating manual included with the indoor unit for details on how to run the unit in heating mode.) The water supply will start and the humidifier will begin operation.
In case of finding a problem at a trial operation In case of finding a problem at a trial operation Symptom Check Item The Product doesn't work Is power not supplied? Counter-measure Supply Power The Product doesn't work through Is the Indoor temperature less you press the 'ON' switch than 45°c or more than 40°C? It's standby mode for protecting Total Heat Exchanger.