If the actual pressure is higher than shown, the system is most likely over-charged, and charge should be removed. If the
actual pressure are lower than shown, the system is most likely undercharged, and charge should be added.
NOTICE
Settlement of outdoor unit
1 Fix the outdoor unit with a bolt and nut
(ø10mm) tightly and horizontally on a concrete or rigid
mount.
2 When installing on the wall, roof or rooftop, anchor the
mounting base securely with a nail or wire assuming the
influence of wind and earthquake.
3 If the vibration of the unit is transmitted to the pipe,
secure the unit with an anti-vibration rubber.
Evaluation of the performance
Operate the unit for 15~20 minutes, then check the system
refrigerant charge:
1 Measure the pressure of the gas side service valve.
2 Measure the air temperature from inlet and outlet of air
conditioner.
3 Ensure the difference between the inlet and outlet
temperature is more than 8°C.
4
For reference; the gas side pressure at optimum
condition is shown on table (cooling)
The air conditioner is now ready to use.
Bolt
Tubing connection
Discharge
temperature
Discharge air
Intake temperature
1. Check that all tubing and wiring are properly connected.
2. Check that the gas and liquid side service valves are
fully open.
Prepare remote controller
1 Open the bottom of remote control with turning it
clockwise.
2 Insert the battery. (Match the metal terminals between
remote control and battery.)
3 Align the lines with each other, close the bottom of the
remote control with turning it counterclockwise.
Remove the batteries from the remote controller if the
system is not used for a long time
NOTICE
Metal terminal
1
2
Bottom
Test Running
Refrigerant
Outside ambient
TEMP.
The pressure of the gas side
service valve.
R-22 35°C (95°F)
4~5kg/cm
2
G
(56.8~71.0 P.S.I.G.)
R-410A 35°C (95°F)
8.5~9.5kg/cm
2
G
(120~135 P.S.I.G.)