3 Working with the FB editor
3.8 Inserting complete interconnection from reference project
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
4. Press Insert button.
The button can only be activated if the device in the reference project has the same de-
vice type and version as the project device.
After the button has been pressed, the module assembly is compared. If there are rele-
vant deviations, the insertion is refused and a corresponding message is displayed.
If an insertion is possible, you are asked if the FB interconnection is to be inserted.
5. Confirm the question if the copied FB interconnection is to be inserted with Yes.
The FB interconnection is inserted and the Insert from referential project dialog box is
closed.