Leidos Security Detection & Automation, Inc. – Proprietary Page 4 of 26
Figure 2 – Remove Conductors from J26 Connector
7.5.3 Disconnect the Power Supply input AC power cables at the Power Distribution Block
[1200-12283-00 & 1200-12284-00.]
Figure 3 – Disconnect from Power Distribution Block
7.5.4 Disconnect the ground cable [1200-12294-00] from the ground stud. Remove the four screws
holding the power supply to the bottom of the electrical enclosure then remove power supply and
attached cables.