INSTALLING THE OVERHEAD BEAM 
After positioning the slave column at the designated chalk location; assemble the 
overhead beam on the shop floor to either the narrow or widest lift width hole 
positions as determined by the chalk line measurements. See the photo below for 
illustration. 
While the overhead beam is still on the shop floor install the provided 4 pulleys 
(sheaves). Two (2) pulleys on each side of the overhead beam using the parts 
shown below. Note: Asymmetric installation (rotated column position as shown in 
figure 5) requires the pulleys to be installed offset to each other using two (2) 
axles and related parts. Symmetric installation (as shown in figure 4) requires the 
pulleys to be installed on a common axle using the related parts. See related 
photos below.   
Note:
Some TLT210 series models may already
have the pulleys installed. The TLT211-AS model has     
the pulleys pre-installed at the factory. If this is case, 
disregard the instructions below and proceed to the 
next phase of installation.
Photo below shows the overhead 
beam assembled at the widest 
(most common) position.