User Manual

Table Of Contents
Landis+Gyr Chapter 17 - Sprague GPR-P Index Cover & GPR Install
Installation Guide 98-1135 Rev AA 95
Figure 17 - 5. Excess Coiled Cable Attached Beneath GPR Bracket
Figure 17 - 6. Excess Coiled Cable Attached Beneath GPR Bracket
U WARNING: Take care not to pinch the index cover switch cable assembly in any way,
especially during the following installation steps:
During index cover and cable assembly installation onto the meter.
During GPR enclosure cover installation.
Between the GPR and meter brackets and meter.
7. Install the Solid State Pulser index cover and GPR assembly over the meter dial index as shown
in the next figure. The cover must be installed with the 1/8 inch thick cork gasket provided with
the Solid State Pulser index kit.
Figure 17 - 7. Switch Wires Must Not Interfere With Index Pointers
Loosely
secure the
excess cable
to the bracket
with a black
zip tie