3.2 Utility or municipal authorization for pole
attachment
The Below statement is a placeholder until statement can be reviewed.
When the Concentrator is to be located on utility or municipal property such as utility poles and
streetlight poles, Cellnet will have a general agreement in place to install on these poles. There
may be a requirement for the utility or municipal to approve individual sites. This approval will be
noted on the Concentrator installation sheet or provided in another format approved by Cellnet. It
is the contractor’s responsibility to ensure that approval has been given for each installation.
4.0 Site location and verification
4.1 Site verification
The Below statement is a placeholder until statement can be reviewed.
The contractor shall be responsible for installing the Concentrator on the correct pole or building.
The contractor should make every effort to confirm that they have the correct location.
4.2 Bucket trucks
The Below statement is a placeholder until statement can be reviewed.
The contractor shall provide a bucket truck for installations requiring them. A bucket truck is used
for most wood and streetlight pole installations. The contractor shall comply with all local traffic
ordinances while performing the Concentrator installations.