Cod. 2850017 - Rev.
TECHNICAL CHARACTERISTICS Dimensions: Height 62 cm Width 42 cm Depth 40 cm Weight: 35 Kg Voltage supply: 230 Vac. 50 Hz or 120 Vac. 60Hz on request LEGEND F VA D CV P V C Ev1 Ev2 Ev3 EvE WATER FILTER ONE-WAY VALVE ANTI-LIMESTONE FILTER (optional) FLOWMETER PUMP ONE-WAY VALVE BOILER TEA OR SOLUBLE COFFEE VALVE MILK & CHOCOLATE VALVE HOT WATER VALVE (OPTIONAL) ESPRESSO COFFEE VALVE GE ESPRESSO GROUP S WASTE Absorbed power: 1,6 KW Selections: 11 selections.
WATER FLOW DIAGRAM GRINDER The quantity of ground coffee is adjustable through a screw (2); screwing it the quantity decreases, while unscrewing it, the quantity increases.. To adjust the degree of grinding, after having pushed the lock (6), act on the grind-stone holder (1), clockwise to have a finer grinding, while in counterclockwise to obtain a bigger grinding. Make sure that the lock comes back in the hole of block of the grind-stone holder, before starting the grinder. Pag. 26 Pag.
INSTALLATION Before installing the machine, read carefully this manual. Install the machine in a dry and hygienic place. ELECTRIC CONNECTION Before connecting the machine to an electric plug, please follow these precautions: • The main supply must correspond to the power requirements of the machine (1600W). • Check that the power supply voltage correspond to the voltage shown in the rating label. • Check that the main socket is correctly earthed.
ELECTRICAL DIAGRAM HYDRAULIC CONNECTION The machine could be installed on: • • a cabinet with place for cups, spoons and sugar and a water tank of 15lt a small base with waste containers (the machine has to be with mains water connection). On cabinet Place the dispenser on the base and fix it with the screws. Fill up the special water tank with potable water, insert the tube with the filter and the one-way valve , and if it's present, the float. Insert in the tank of 5 lt. the waste pipe.
SWITCHING ON After having followed all the instructions of installation, it is possible to turn on the machine through the light switch situated on the frontal side of the electric panel. At the switch on of the machine, it appears on display for a brief time the message of the version software, after that it will begin the heating of the boiler that will be visualized with the message" HEATING" that will be replaced, to reached temperature, from the flowing message". ….
QUICK FUNCTIONS In this section, it is possible to perform some of the most useful functions by the loader. To access press the button “QUICK MENU” of the keyboard (see page 6). On display you will see “QUICK MENU ” Pushing the relative number, you will execute these following functions:: 1. mixers washing: a washing for each mixing group is executed. 2. boiler 1 temperature visualization: you see for 2 seconds the present temperature of the boiler 1. 3.
SET DRINKS Entering the program through E, you will see the sequence of the existing drink codes. 01-02-03-04-05-0 Sel.1 The flashing cursor points out the drink code selected, to move it use the keys + to advance or - to withdraw; contemporarily to the movement of the cursor, in the underlying line, the name of the selection will be visualized related to the drink code. To modify the parameters of the drink code press E.
It is possible to eliminate, to modify or to insert movements or to change its regulations where possible, for example the dosing of the products.
COUNTERS & AMOUNTS SET DRINKS In this menu it is possible to notice the counters of the various selections and eventually to reset them. Premise: every selection or drink it is composed from a sequence of movements which correspond to a single operation of the machine. The single movements are only performed after the correct event of the previous movement, in case of not-correct operation the machine will go to alarm.
Electrical OUTPUT EVENTS In this menu it is possible to notice the last 100 events of the machine. Entering the menu with ENTER the following data will be visualized: N° description Date : hour & date ID:XXX RESULT POS 1 Not used 2 Grinder motor 3 Coffee releaser solenoid 4 Espresso unit motor 5 ETV espresso 6 Pump 7 ETV / whipper sol. 1/2 (milk / chocolate) 8 Powder motor sol.1 (milk) 9 Not used Internal operation codes 10 Powder motor sol. 2 (chocolate) 11 ETV / whipper sol.
MAIN MENU RESET COUNTERS&AMOUNTS: Reset of all the counters above. Press “6” to confirm or “5” to cancel. To access this menu, keep pressed the button PROG for 5 seconds. ENABLE SLAVE MACHINE Enable the “slave” machine (not available). The menu is composed by the followings programs: ENABLE TEMPERAT.ON DISPLAY: Visualization on display of the boiler temperature. PAYMENT SYSTEM Setting of the system of payment and its options. SERIAL NUMBER: set the serial number of the machine.
OPTIONS: LEVEL 2 (manager- technician) PAYMENT SYSTEM After having inserted the correct password, that it initially is" ask to manufacturer", you will enter in the following menu: The followings programs compose this menu: MODIFY PASSWORD LEVEL 1: Insert the new password and press E to confirm. MODIFY PASSWORD LEVEL 2: Insert the new password and press E to confirm. SET COIN VALUE PARALLEL SYSTEM Setting of the coin values (see note 1).
SET TEMPERATURE OPTIONS: LEVEL 1 (operator) The followings programs compose this menu: After having inserted the correct password, which initially is "ask to the manufacturer”, the following menu will compare: SET BOILER 1 TEMPERATURE Set-up of the boiler 1 temperature. TIME OVERHEATING BOILER 1 After this time of “machine stopped” the boiler 1 is overheated. SET OVERHEATING BOILER 1 Value of overheating of the boiler 1 (max. 5°C).