2.2.2.1 Set the Master battery (ONLY!!!) DIP address according to the User Manual (Picture above).
2.2.2.2 Press the Master battery reset button to switch on all the batteries and then close the battery breaker
2.2.2.3 Close inverter switch, then turn on DC breaker to start MPPT.
2.2.2.4 Switch on AC input and output breaker
2.2.3.1 Conrm the rmware version
2.2.2 START SYSTEM
2.2.3 INVERTER SETUP
MPPT
INSTALACJA PV
PV INSTALLATION
PE
VE Direct/VE CAN
BMS CAN
VE Bus
Wyjście AC2
AC2 out
Wyjście AC1
AC1 out
LINK OUT - PORT OSTATNIEGO AKUMULATORA SLAVE WOLNY
LINK OUT - LAST SLAVE BATTERY PORT NOT CONNECTED
Wejście AC1
AC1 in
Sieć
energetyczna
GRID
Cerbo GX
MultiPlus II 3K
Ostatni akumulator Slave
Last Slave battery
Akumulator Master
Master battery
DIP: 0000000
n - równolegle
n - parallel
Rozłącznik DC
DC Breaker
Rozłącznik DC
DC Breaker