Instruction Manual

Secure the baseplate to the surface using the fixings provided
Connect the luminaire to the mains supply ensuring the correct polarity is observed:
L – Live, K – Switched Live (brown), N - Neutral (blue) (see Fig. 3)
Fig. 2
Connect the battery to the socket on the emergency inverter
Close the hinged gear tray until the tab clicks into position
Reattach the diffuser and secure with the three screws, ensuring the seal is in place
and not damaged
Switch on and check for correct operation ensuring the green indicator LED is illuminated
We recommend, on commissioning the installation, a minimum charge period of 24
hours before carrying out an emergency duration test
If the batteries have been left in a discharged state for an extended period, we
recommend one or more charge and discharge cycles are completed which should help
to restore the battery capacity
Fig. 3