Instruction Manual
•
•
•
•
•
•
•
•
•
•
•
•
•
•
• Secure the baseplate to the surface using the fixings provided
• Connect the luminaire to the mains supply ensuring the correct polarity is observed:
L – Live, K – Switched Live (brown), N - Neutral (blue) (see Fig. 3)
Fig. 2
•
•
•
•
•
•
• Connect the battery to the socket on the emergency inverter
• Close the hinged gear tray until the tab clicks into position
• Reattach the diffuser and secure with the three screws, ensuring the seal is in place
and not damaged
• Switch on and check for correct operation ensuring the green indicator LED is illuminated
• We recommend, on commissioning the installation, a minimum charge period of 24
hours before carrying out an emergency duration test
• If the batteries have been left in a discharged state for an extended period, we
• recommend one or more charge and discharge cycles are completed which should help
to restore the battery capacity
Fig. 3