TESTING FOR EMERGENCY LUMINAIRES
Recommended routine test procedure in accordance with BS5266.
Initial commissioning test - We recommend a minimum charge period of 24 hours before completing
an initial commissioning emergency duration test
Daily check – check that the status GREEN LED indicator is illuminated.
Monthly functional test – simulate a mains supply failure for approx. 30 secs by operation of key
switch or switching off a circuit breaker. Ensure normal supply is restored after test and the indicator
status LED is illuminated.
Annual full three hour duration test - conduct a three hour continuous duration test. Simulate a
mains supply failure for three hour continuous test by operation of key switch or switching off circuit
breaker. Ensure normal supply is restored after test and the indicator status LED is illuminated.
If the luminaire fails any of the above tests, please contact a qualified electrician.
TEST RECORD SHEET
INITIAL COMMISSIONING
3 HOUR TEST
SIGNED DATE
MONTH TEST
FIRST YEAR SECOND YEAR THIRD YEAR FOURTH YEAR FIFTH YEAR
SIGNED DATE SIGNED DATE SIGNED DATE SIGNED DATE SIGNED DATE
1 FUNCTIONAL
2 FUNCTIONAL
3 FUNCTIONAL
4 FUNCTIONAL
5 FUNCTIONAL
6 FUNCTIONAL
7 FUNCTIONAL
8 FUNCTIONAL
9 FUNCTIONAL
10 FUNCTIONAL
11 FUNCTIONAL
12 3 HOUR
Installed by: Installation date: