INSTALLATION & MAINTENANCE MANUAL EMLED1 230V 50Hz IP 65 54
GENERAL INSTRUCTIONS These instructions should be read carefully and retained after installation by the end user for future reference and maintenance.
Battery PCB Fig 3 • For maintained non-switched operation, carefully wire as shown in Fig 4 Battery PCB Fig 4 • Connect the battery to the inverter via the plug and socket provided • Refit the gear tray by pushing down until the tabs click into place • Place diffuser in line with the 2 screw holes and fasten screws down • Switch on the power supply and ensure the LED indicator is illuminated Green.
TESTING FOR EMERGENCY LUMINAIRES Recommended routine test procedure in accordance with BS5266. Initial commissioning test - We recommend a minimum charge period of 24 hours before completing an initial commissioning emergency duration test Daily check – check that the status GREEN LED indicator is illuminated. Monthly functional test – simulate a mains supply failure for approx. 30 secs by operation of key switch or switching off a circuit breaker.