Verify site preparation and physical installation are completed: (see Alcatel-Lucent RRH2x60-B4 – Site
Preparation Guidelines, 3MN-01520-0001-RJZZA):
3. Tools, materials, and prerequisites – Prerequisites
Before installation of the Alcatel-Lucent RRH2x60-B4 site can begin, site preparation must be completed.
The following site preparation general requirements must be met before the installation of the Alcatel-Lucent
RRH2x60-B4 can begin:
Adequate clearance must be provided for service access
DC electric service (with a readily accessible disconnect device ) must be installed
User alarm facilities must be installed Grounding electrode system must be installed and tested
RF and antenna runs must be installed (if required) Surge protection for antennas must be installed (if required)
Tower light power must be installed (if required) Tower light alarm must be installed (if required)
The environment must comply with limits listed under Environmental requirements in the Alcatel-Lucent
RRH2x60-B4 – Site Preparation Guidelines, 3MN-01520-0001-RJZZA
Cable supports and racks must be installed Conduit for DC power must be installed when applicable
Installation
p
rocedure checklist
Done N/A Task
5-1: Install RRH on a pole
5-2: Install RRH on a wall
5-3: Procedure to chan
g
e from T
yp
e A confi
g
uration to T
yp
e B
p
gypg
yp
5-4: Connect protective earth (PE) ground
5-5: Connect optical fiber cables
5-6: Route and connect user alarm cables (optional)
5-7: Route and connect AISG cable
(
o
p
tional
)
Alcatel-Lucent RRH 2x60-B4
Alcatel-Lucent – Internal
Proprietary – Use pursuant to Company instruction
3MN-01520-0002-RJZZA Issue 0.02 March 2014
Sheet 10 of 24
(p )
5-8: Route and connect RF cables (optional)
5-9: Connect DC power cable
5-10: Final checks prior to installation