Installation Guide

Installation Guideline for 3D wood wall Collection
3D wood wall panel must be installed according to the installation guide and maintained in an environment where the humidity
is between 35% and 60%Do not install panels in bathrooms, shower rooms, or other rooms exposed to excessive. Allow a
minimum of 48 hours to acclimatize the products
Required Tools:
Electric drill, 100% polyurethane glue, level, pencil, measuring tape, saw (circular, miter or table, Jigsaw); step ladder,
pneumatic nailer and nails.
Preparation:
Remove all accessories, moldings and electrical outlets from the wall where product is to be installed
Ensure that the surface to be covered with 3D wood wall panel is firm and leveled. Uneven areas must be adjusted.
If necessary, remove loose paint using a painters knife. Optionally, a 3/8”(9.52mm) thick plywood can be applied over the
drywall if wall is in poor condition. Clean and wipe the wall dry.
Before installing, plan the placement of each panel. There are naturally occurring characteristics including but not limited
to color variation, knots, pin holes , warm holes, mineral streaks, varying surface textures. These characteristics are a
desired result of the aging of a natural material. If the wall panels are considered unacceptable STOP DO NO INSTALL
IT”. Once installed, there is no questions as to its acceptability.
Leave a 1/2”(12.7mm) expansion gap at the perimeter and around all obstacles gap to allow the expansion and contraction
of the wood. This gap will be coverd by molding at the end the project.
Note: Cutting around electric outlet
Measure the wall outlet and add 1/2”(12.7mm) to each size of the wall outlet
One the panel, identify where you need to cut and trace a box for the outlet using a black marker
Drill into the 4 corners of your marking, then use a jigsaw to cut out the square of the outlet.
Reinstall the electric outlet cover after completing the installation of the wall panels
Installation instructions:
1. Please do not follow the ceiling or floor as a level line, as it may not be leveled. Usually start the installation from left to
right, and top to bottom. Firstly finish one horizontal row and then move to next one.