Network Router User Manual
Chapter 5
Preparing for Router Installation
This chapter describes how to prepare your site for installation of the M10i Internet
router. It discusses the following topics:
■ Site Preparation Checklist on page 41
■ Rack Requirements on page 42
■ Clearance Requirements for Airflow and Hardware Maintenance on page 44
Site Preparation Checklist
The checklist in Table 14 on page 41 summarizes the tasks you need to perform
when preparing a site for router installation.
Table 14: Site Preparation Checklist
DatePerformed ByFor More InformationItem or Task
Environment
“Router Environmental
Specifications” on page 173
Verify that environmental factors such as
temperature and humidity do not exceed router
tolerances.
Power
“DC Power, Connection, and Cable
Specifications” on page 179
Measure distance between external power
sources and router installation site.
“Chassis Grounding” on page 177Locate sites for connection of system
grounding.
“Router Power
Requirements” on page 176
Calculate the power consumption and
requirements.
Hardware Configuration
“Hardware Component
Overview” on page 7
Choose the configuration.
Rack
“Rack Requirements” on page 42Verify that your rack meets the minimum
requirements for the installation of the router.
Site Preparation Checklist ■ 41