Network Router User Manual

Chapter 5
Preparing for Router Installation
This chapter describes how to prepare your site for installation of the M10i Internet
router. It discusses the following topics:
Site Preparation Checklist on page 41
Rack Requirements on page 42
Clearance Requirements for Airflow and Hardware Maintenance on page 44
Site Preparation Checklist
The checklist in Table 14 on page 41 summarizes the tasks you need to perform
when preparing a site for router installation.
Table 14: Site Preparation Checklist
DatePerformed ByFor More InformationItem or Task
Environment
Router Environmental
Specifications on page 173
Verify that environmental factors such as
temperature and humidity do not exceed router
tolerances.
Power
DC Power, Connection, and Cable
Specifications on page 179
Measure distance between external power
sources and router installation site.
Chassis Grounding on page 177Locate sites for connection of system
grounding.
Router Power
Requirements on page 176
Calculate the power consumption and
requirements.
Hardware Configuration
Hardware Component
Overview on page 7
Choose the configuration.
Rack
Rack Requirements on page 42Verify that your rack meets the minimum
requirements for the installation of the router.
Site Preparation Checklist 41