SECTION 6 - JLG CONTROL SYSTEM
3121171 – JLG Lift – 6-69
6. Once “CHECKING BOOM…” is started, the control system
will wait 2 seconds and then capture the position of the
Main Boom to Tower, Tower Cylinder Angle and Tower
Length. The control system then will command the Main
Lift, Tower Lift and Tower Telescope PVG valves to 40%,
engage the Main Control and PVG enable valves and
command the Engine to 1800 RPM for 20 seconds. The
control system will monitor for the Main Lift and Tower
Lift angles increasing by more then 0.2 deg and the
Tower Telescope length increasing by more then 0.5”. If
one of these conditions occur the test will abort and dis-
play on the top line “CHECK FAILED:” and “MN LIFT
ENABLE”, “TWR LIFT ENABLE” or “TWR TELE ENABLE” on
the bottom line depending on which section moved.