Installation Guide
2
Installation Instructions
for Wood Patio Doors without Exterior Trim or Nail Fin (JII027)
Landings
These instructions cover two patio door sill conditions: the step-down
landing and the continuous slab landing. The installation methods vary
slightly between landing types.
LANDINGS
ROUGH OPENINGS
Step-Down Landing Continuous Slab Landing
Fully Sheathed Wall Construction
Sheathing is applied to the exterior of the wall framing. The patio
door will be mounted ush against the sheathing or building wrap in a
weatherproof manner.
This installation guide only addresses masonry/block wall, sheathed wall
and open-stud construction. If installing into an opening other than what
is identied, consult a building professional.
Masonry/Block Wall Construction
This installation assumes that a framework of studs (often called a buck)
has already been properly fastened in a weatherproof manner to the
concrete/masonry wall.
Masonry/Block
Wall Construction
Buck
King
stud
Trimmer
studs
Sheathing
Sill Area
Header
Fully Sheathed
Wall Construction
Open-Stud Construction
Sheathing is absent and building wrap is applied atop of the wall framing.
The patio door will be mounted ush against building wrap and/or
framing members (studs).