Installation Guide

English | 2
WALL INSTALLATION (Continued)
2 | Determine the HardieBacker
®
Cement Board with HydroDefense
Technology layout
• Boards may be installed vertically or horizontally.
Edges of the board parallel to framing must be supported by a structural
framing member.
• Score and snap boards to required sizes and make necessary cutouts.
3 | Attach the HardieBacker
®
Cement Board with HydroDefense
Technology to framing
HardieBacker
®
Cement Board with HydroDefense
Technology has internal
waterproofing treatments. Does not require a moisture barrier.*
Attach the HardieBacker
®
Cement Board with HydroDefense
Technology.
Provide a 1/4 in. clearance gap between the floor, tub or shower receptor
base and the cement board.
• Do not place cement board into the shower pan mortar bed.
Fasten the product with specified nails or screws (as listed in “Materials
Required”) a maximum of 8 in. on center at all supports.
Keep fasteners 3/8 in. from board edges and 2 in. in from sheet corners.
Set fastener heads flush with the surface, without overdriving.
4 | Joints and Penetrations
Seal fixture penetrations, plumbing penetrations and abutments to dissimilar
materials with flexible sealant (see “Materials Required”).
Fill all joints with mortar (see “Materials Required”). While mortar is still
workable, embed minimum 2 in. wide high-strength alkali-resistant glass
fiber tape in the mortar and level.
• Do not use all-purpose joint compound or paper tape.
When complete waterproofing is required, seal all joints, edges and fastener
penetrations with a liquid waterproofing membrane. Follow the liquid
waterproofing membrane manufacturer application instructions.
* Some application areas may require additional waterproofing. Refer to local building code requirements.