Installation Sheet
www.jacuzzi.com Page 9
Installation
English
Installation Procedures (cont.)
Undermount Installation
1. Inspect all ttings, plumbing, and control lines after inserting to ensure the components
are not damaged or disconnected.
2. Align the bathtub and connect the drain.
3. Cut deck to t using the undermount template provided as follows:
• Position the template so that the desired undermount guidelines are aligned with
the rim edge as shown.
• Using a grease pencil, mark the center lines (denoted by
L
C
on template). Remove
template.
• Measure the distance from the wall, or other xed point, to the center lines, Figure 8.
4. Afx counter to bathtub. Clean any dirt or debris from the top of the bathtub rim.
5. Turn on the power supply to the dedicated GFCI-protected circuits and check
system operation.
CAUTION! Do not use an adhesive or adhesive sealant to secure the
bathtub to the deck. If maintenance or remodeling is required, the deck
may have to be removed. Adhesive will permanently bond the bathtub to
the deck. Carefully position the deck over the bathtub. Follow
manufacturer’s instructions to determine cure time.
6. Apply a continuous bed of silicone sealant around the entire seam between the counter and the bathtub rim. Allow
sealant to cure according to manufacturer’s instructions, Figure 9.
3-Wall Alcove Installation
1. Make sure framed-in alcove is of proper size per Jacuzzi dimensions, square, and
plumb; check oor for levelness (Figure 10). Rough-in should be kept to a minimum
until the unit is on the job site. Measurements may vary +0 or -¼" from original
specications.
2. Place the tub in the alcove with the front skirt rmly on the oor. The bathtub must
be set level. To check, use a level on top of the ledges on both ends of tub and on
top of dam (Figure 10).
3. After leveling tub, mark each stud (concrete or block wall) immediately above the
back horizontal ange. Remove tub from alcove. Measure the distance between
the top of the back horizontal ange and the bottom of the tub ledge approximately
1½" (40 mm). Carefully mark this dimension on the back studs (or wall), below the rst
mark (Figure 11 - inset).
4. Install a Ledger Strip: Jacuzzi mandates the use of supports
under the rear ledges of bathtubs to prevent shifting. Use
horizontal ledger strip along the entire rear ledge or “I”, “T”
supports in at least two places in vertical position. Nail a 1" x 3"
(25 mm x 75 mm) ledger strip immediately below the lower marks
made on framing (Figure 11 - inset).
5. When fastening wood framing, pre-drill anges with a ⅛" (5 mm)
carbide bit and fasten using #8 x 1-½" (38 mm) self-tapping sheet
metal screws; to concrete/block walls use 1" (25 mm) concrete
nails with nailing tool or impact.
NOTE: Pre-drilling and nailing anges is recommended to avoid
cracking of the acrylic unit. Silicone the top of each fastener to insure
water tightness.
Template
Counter
A
B
C
D
Fig. 8
Fig. 9
Template
Bathtub Rim
Seal with
silicone sealant
Level
Fig. 10
Ledger
Board
Top of
Ledger Strip
1.50"
Fig. 11