Figure 51PLC Signal Cable Insertion Location
7. Route he PLC Signal Cable through the hole, see item.
8. Secure the Cable Gland into the threaded hole, as shown. Use a 15/16" combination wrench
to secure the cable gland.
Figure 52PLC Signal Cable and Cable Gland Location
9. Insert the PLC Signal Cable into the 6-Pin connector, see item 1, on the front of the
CAM3S/CAM3M.