5
Radio Frequency and Power Line Carrier
Installation
This chapter covers the following topics:
■
Disconnecting Power to the CGR
■
Installing the CAM3S/CAM3M Using the PLC Signal Cable
Disconnecting Power to the CGR
1. Disable the power at the circuit, or power supply that the CGR AC Power Cable is
connected.
2. Disconnect the CGR AC Power Cable, see item 1, from the AC Power Connector located
on the bottom exterior of the CGR enclosure.
Figure 44AC Power Cable Connection Location
3. Loosen the six captive bolts that secure the hinged CGR door using the sequence shown
below and swing the door fully open. Use a 1/2" (13mm) socket wrench and apply a torque
of 3 to 4 foot pounds (ft-lb).
02 March 2020 815-0080-00 Itron, Inc. Page 50 of 102