8. Continue wrapping the vinyl electrical tape in a spiral back down to the filter. You should now
have two layers of vinyl electrical tape covering the Butyl rubber.
Reinstalling the Power and Ground to the CGR
After installing the new CAM3S and the remote antenna, you can reconnecting power and
ground the CGR, attaching the lightning arrestor, and weatherproofing the connections.
Caution: If Ethernet is used, the cable length must not exceed two meters in total.
Lengths longer than two meters are not approved and do not meet FCC and ISED
compliance requirements.
1. Reinstall the 6AWG Ground Cable, see item 2, located on the bottom right side of the CGR
using the two screws into the ground lug, see item 1.
Figure 386AWG Ground Cable and Ground Lug Location
2. Enable the power at the circuit, or power supply that the CGR AC Power Cable is
connected.
3. Install the CGR AC Power Cable, see item 1, to the AC Power Connector located on the
bottom exterior of the CGR enclosure.
02 March 2020 815-0080-00 Itron, Inc. Page 45 of 102