Installation Guide
Table Of Contents
- OpenWay® Riva CAM3S and CAM3M Installation Guide
- Table of Contents
- New in this Document
- 1 About This Guide
- 2 Introduction
- 3 Installation Kits
- 4 Star and Mesh Deployment Installation
- 5 Radio Frequency and Power Line Carrier Installation
- 6 ACT Coupler Unit Installation (CAM3M Only)
- 7 Replacing an Existing CAM with a New CAM3S/CAM3M in the Field
- A Specifications
- B RF Filter Installation
- Glossary
- Index
■
1/2" (13mm) socket wrench.
■
A #2 Phillips or a 9/32" flat-blade screwdriver.
■
15/16" combination wrench.
Order of Installation
In general, this provides the order of installation that should be followed.
1. Disconnecting Power to the CGR.
2. Removing the CGR from the pole.
3. If applicable, removing the RF Filter from the pole. See Connecting a RF Filter
and simply reverse the connection order.
4. If applicable, removing an existing CAM.
5. Installing the CAM3S/CAM3M.
6. Reinstalling the CGR back on the pole. If required, include a RF Filter. See RF
Filter Installation.
7. Reinstalling Power and the Ground to the CGR.
8. Installing the Lightning Arrestor to the CGR.
9. This step is only applicable for a CAM3S. Installing the Remote Antenna on the
pole (five feet vertical distance from the CGR),
Disconnecting Power to the CGR
1. Disable the power at the circuit, or power supply that the CGR AC Power Cable is
connected.
2. Disconnect the CGR AC Power Cable, see item 1, from the AC Power Connector located
on the bottom exterior of the CGR enclosure.
02 March 2020 815-0080-00 Itron, Inc. Page 23 of 102
OpenWay® Riva CAM3S and CAM3M Installation Guide 4 Star and Mesh Deployment Installation