Certification Exhibit FCC ID: SK9OW1 IC: 864G-OW1 FCC Rule Part: 15.247 IC Radio Standards Specification: RSS-247 ACS Project Number: 16-0295 Manufacturer: Itron, Inc. Model: OW1 Manual 5015 B.U.
OW1 OpenWay® Riva™ CAM / ACT Technical Reference Guide Effective Date: August, 2016 CAM Module, Model OW1
Revision History The following table describes the changes to this document for each revision of the OW1 module: Revision A Date Description of Change August, 2016 Initial Release CAM Module, Model OW1
Labeling The following requirements will be applied to any products that use this module: The end product or host label will include the following text: • • • Contains: FCC ID: SK9OW1 IC: 864G-OW1, Model: OW1 The user’s manual for any product that contains this module will contain the following text. If the device is large enough, then this will also be placed on the label. “This device complies with Part 15 of the FCC Rules.
Under Innovation, Science and Economic Development Canada regulations, this radio transmitter may only operate using an antenna of a type and maximum (or lesser) gain approved for the transmitter by Innovation, Science and Economic Development Canada. To reduce potential radio interference to other users, the antenna type and its gain should be so chosen that the equivalent isotropically radiated power (e.i.r.p.) is not more than that necessary for successful communication.
Installation The OW1 module will be installed in the Cisco 1240 CGR.
OpenWay® Riva™ CAM / ACT Coupler Unit Installation Guide OpenWay® Riva™ CAM / ACT Coupler Unit
Contents About This Document ................................................................................................... 1 Installation Kits .............................................................................................................. 3 CAM Installation Kit .............................................................................................................................3 Coupler Unit Installation Kit .......................................................................
Contents OpenWay® Riva™ CAM / ACT Coupler Unit Installation Guide iv
CHAPTER 1 About This Document This document provides the procedure necessary to install the CGR ACT Module (CAM) and the ACT Coupler unit (ACU) with the 1000 Series Cisco Grid Router (CGR). In addition to the physical installation of the Adaptive Communications Technology (ACT) module and ACU, a procedure for loading the actd application into the CGR Guest Operating System (GOS) is also provided. The actd application serves as a communication gateway between the IOS and the CAM.
About This Document OpenWay® Riva™ CAM / ACT Coupler Unit Installation Guide 2
CHAPTER 2 Installation Kits CAM Installation Kit The following items are included in the CAM installation kit. 1 - CGR ACT (OW1) module 1 - Regulatory label Coupler Unit Installation Kit The following items are included in the ACT Coupler Unit installation kit.
Installation Kits OpenWay® Riva™ CAM / ACT Coupler Unit Installation Guide 4
CHAPTER 3 CAM Installation for RF Only Applications The following procedure is for CAM installations that are for RF only. Open CGR Door Illustration Callout Number 1 Description CGR door retaining bolts 1. Loosen the six captive bolts that secure the hinged CGR door using the sequence shown below and swing the door fully open. Note The CGR door features an environmental seal that protects the unit against environmental elements when the door is closed.
CAM Installation for RF Only Applications Illustration Callout Number 1 Description Slot #5 slot with blank cover 2. Loosen the two captive screws on the blank cover over slot #5 and remove the cover. Use either a #2 Phillips or a 9/32" flat blade screwdriver.
CAM Installation for RF Only Applications Install CAM for RF Only Applications Illustration Callout Number 1 Description Slot #5 identifier label 2 CAM (OW1) 3 CAM retaining screws 1. Locate slot #5 by the slot identifier label inside the CGR. 2. Insert the CAM in slot #5 of the CGR. Ensure the CAM is oriented so that the connectors on the rear of the CAM are aligned with those in the slot #5.
CAM Installation for RF Only Applications Illustration Callout Number 1 Description Antenna cable connection 2 WPAN antenna 4. Secure the black antenna wire from the WPAN antenna to the bottom antenna connector on the front of the CAM. 5. Ensure the antenna cable is routed so that it does not interfere with door closure. Use a single plastic cable tie to secure the antenna cable to the tie loop on the front of the CAM. 6.
CAM Installation for RF Only Applications 7. Affix the regulatory label (included in the CAM installation kit) to the bottom of the CGR in the label location provided between the antennas.
CHAPTER 4 CAM Installation for RF/PLC Applications The following procedure is for CAM installations that are RF and PLC applications. Open CGR Door Illustration Callout Number 1 Description CGR door retaining bolts 1. Loosen the six captive bolts that secure the hinged CGR door using the sequence shown below and swing the door fully open. Note The CGR door features an environmental seal that protects the unit against environmental elements when the door is closed.
CAM Installation for RF/PLC Applications Illustration Callout Number 1 Description Slot #5 slot with blank cover 2. Loosen the two captive screws on the blank cover over slot #5 and remove the cover. Use either a #2 phillips or a 9/32" flat blade screwdriver.
CAM Installation for RF/PLC Applications Install CAM for RF/PLC Applications Illustration Callout Number 1 Description Slot #5 identifier label 2 CAM (OW1) 3 CAM retaining screws 1. Locate Slot #5 by the slot identifier label in the CGR. 2. Insert the CAM in slot #5 of the CGR. Ensure the CAM is oriented so that the connectors on the rear of the CAM are aligned with those in the slot #5. Gently press the CAM until the card-edge connector on the CAM is firmly seated into the connector in the CGR. 3.
CAM Installation for RF/PLC Applications Illustration Callout Number 1 Description PLC signal cable plug 4. Remove the PLC signal cable hole plug using a 13mm socket wrench.
CAM Installation for RF/PLC Applications Illustration Callout Number 1 Description PLC signal cable connection routing 5. Insert the PLC signal cable into the CGR.
CAM Installation for RF/PLC Applications 6. Route the PLC signal cable through access hole and secure the cable gland into the threaded hole. Use a 15/16" combination wrench to secure the gland.
CAM Installation for RF/PLC Applications Illustration Callout Number 1 Description PLC signal cable connection 7. Insert the PLC signal cable into the connector on the front of the CAM.
CAM Installation for RF/PLC Applications Illustration Callout Number 1 Description Antenna cable connection 2 WPAN antenna 8. Secure the black antenna wire from the WPAN antenna to the bottom antenna connector on the front of the CAM.
CAM Installation for RF/PLC Applications . Illustration Callout Number Description 1 PLC cable 2 Antenna cable connection 3 Plastic cable tie 9. Ensure the cables are routed so that they do not interfere with door closure. Use a single plastic cable tie to secure the PLC cable and the antenna cable to the tie loop on the front of the CAM. 10. Close the door and secure by tightening the six captive bolts using the sequence shown below. Use a torque of 6-7 foot-pounds when tightening the bolts.
CAM Installation for RF/PLC Applications 11. Affix the regulatory label, included in the CAM installation kit, to the bottom of the CGR in the label location provided between the antennas.
CAM Installation for RF/PLC Applications OpenWay® Riva™ CAM / ACT Coupler Unit 20
CHAPTER 5 CGR ACT Coupler Unit Installation This procedure is for installing a Cisco Grid Router (CGR) Adaptive Communications Technology (ACT) Module (CAM) and the ACT Coupler Unit (ACU) to an existing pole mounted CGR application. To install the CGR refer to the CGR installation procedure in the Cisco 1240 Connected Grid Router Hardware Installation Guide. Disconnect CGR Cables Illustration Callout Number 1 Description CGR power cable 1.
CGR ACT Coupler Unit Installation Illustration Callout Number Description 1 Ground Lug 2 CGR 6 AWG ground cable 2. Remove two screws from the ground lug and disconnect the ground cable from the CGR.
CGR ACT Coupler Unit Installation Remove CGR from Mounting Illustration Callout Number 1 Description Mounting bolt to be loosened 2 Mounting bolts to be completely removed 1. Loosen the top front hex head bolt on each side but do not completely remove. 2. Remove the two rear and lower front hex head bolts on each side of the CGR mounting bracket.
CGR ACT Coupler Unit Installation Remove CGR Mounting Bracket Illustration Callout Number 1 Description Hex head mounting bolts 2 Center stud with self-locking hex nut 1. Remove the four hex head bolts and set aside. Longer bolts are required to accommodate the coupler unit bracket and are provided in the ACT Coupler unit installation kit. 2. Loosen the center self-locking hex nut to allow the bracket to slide upward and off the center stud.
CGR ACT Coupler Unit Installation Install Coupler Mounting Bracket Illustration Callout Number 1 Description Center stud with self-locking hex nut 1. Slide the coupler mounting bracket keyhole slot over the center stud on the pole mount base plate.
CGR ACT Coupler Unit Installation Install CGR Mounting Bracket Illustration Callout Number Description 1 Alignment slots 2 4 - Hex head mounting bolts (8mm x 25mm) supplied with the installation kit 3 Center stud with self-locking hex nut 1. Position the CGR mounting bracket over the center stud and slid down behind hex nut. 2. Insert the four 8mm x 25mm mounting screws supplied with the installation kit into the threaded holes in the base mounting plate.
CGR ACT Coupler Unit Installation Install the CGR 1. Mount the CGR to the mounting bracket by sliding the mounting bolt in the top front position on each side of the CGR into the corresponding slot on the mounting bracket. Illustration Callout Number 1 Description Mounting bolt not completely removed 2 Mounting bolts to be completely removed 2. Insert the remaining three bolts on each side of the CGR into their respective places. Note Insert all mounting bolts on each side before securing tightly. 3.
CGR ACT Coupler Unit Installation Connect CGR Cables Illustration Callout Number 1 Description Coupler unit power input bulkhead connector 2 Coupler unit power cable 1. Connect the 5-pin external power supply cable to the left most connector on the bottom of the coupler unit.
CGR ACT Coupler Unit Installation Illustration Callout Number 1 Description Coupler unit power bulkhead connector 2 Coupler unit to CGR power cable 2. Connect the 5-pin male end connector of the coupler unit to CGR power to the power output (center) bulkhead connector on the bottom of the coupler unit.
CGR ACT Coupler Unit Installation Illustration Callout Number 1 Description CGR power bulkhead connector 2 Coupler unit to CGR power cable 3. Connect the 3-pin female end of the coupler unit to CGR power cable to the power input bulkhead connector on the bottom of the CGR.
CGR ACT Coupler Unit Installation Illustration Callout Number 1 Description PLC signal bulkhead connector 2 PLC signal cable 4. Connect the 6-pin male end of PLC signal cable to the PLC bulkhead connector on the ACT coupler unit.
CGR ACT Coupler Unit Installation 5. Connect the 6-pin female end of the PLC signal cable to the male PLC signal bulkhead connector on the CGR.
CGR ACT Coupler Unit Installation Illustration Callout Number Description 1 Ground Lug 2 CGR 6 AWG ground cable 6. Insert the two screws for the ground lug to connect the ground cable to the CGR. Use a torque of 10-12 foot-pounds when tightening the grounding screws.