Setup Guide
Table Of Contents
- Intelis Gas Meter Proving and Setup Guide
- Contents
- New in this Document
- 1 Important Safety and Compliance Information
- USA, FCC Part 15 Spectrum Compliance
- Canada, ISED Spectrum Compliance
- RF Exposure (FCC/ISED)
- Australia, ACMA Spectrum Compliance
- Electromagnetic Compatibility
- Intrinsic Safety
- Lithium Battery
- Transportation Classification
- Electrostatic Discharge
- Electrostatic Ignition Hazard
- Device Cleaning
- Do Not Drop
- Product Standards
- 2 Overview
- 3 Proving
- 4 Proving the Intelis Gas Meter Using the Honeywell SNAP Proving System
- 5 Proving the Intelis Gas Meter Using the Measurement Systems Proving System
- 6 Proving the Intelis Gas Meter Using the Energy Economics (EEI) Proving System
- 7 Calibrating the Intelis Gas Meter
–
% Proof. 100% open, 100% check
–
% Accuracy. 100% open, 100% check
–
% Error. 0% open, 0% check
10. Click Quit or Finish to return to the Tools screen.
11. (Recommended) Rerun the meter on the prover station to verify the meter calibration. It is
expected that you see the results that match the following example:
If the accuracy results are not as expected, repeat the calibration steps.
Note: Prover station accuracy is estimated to be +/- 0.15-0.25%.
To Seal an Intelis Gas Meter
1. From the Tools menu, select Intelis Gas Meter.
2. Select Test Mode Operations.
3. Select Seal Meter.
A progress bar indicates that the meter is sealing.
08 July 2020 815-0154-00 REV 000 Itron, Inc. Page 63 of 66
Intelis Gas Meter Proving and Setup Guide 7 Calibrating the Intelis Gas Meter