Installation Guide
Table Of Contents
- Intelis Gas Meter Installation Guide
- Table of Contents
- 1 Important Safety and Compliance Information
- USA, FCC Part 15 Spectrum Compliance
- Canada, ISED Spectrum Compliance
- RF Exposure (FCC/ISED)
- Australia, ACMA Spectrum Compliance
- Electromagnetic Compatibility
- Intrinsic Safety
- Lithium Battery
- Transportation Classification
- Electrostatic Discharge
- Electrostatic Ignition Hazard
- Device Cleaning
- Do Not Drop
- Product Notification
- 2 Intelis Gas Meter
- 3 Installation
- 4 LCD Operation
- 5 Proving
- 6 Adjusting the Calibration
- 7 Maintenance
9. Click Quit or Finish to return to the Tools screen.
10. (Recommended) Rerun the meter on the prover station to verify the meter calibration. It is
expected that you see the results that match the following example:
If the accuracy results are not as expected, repeat the calibration steps.
Note: Prover station accuracy is estimated to be +/- 0.15-0.25%.
To Seal an Intelis Gas Meter
1. From the Tools menu, select Intelis Gas Meter.
2. Select Test Mode Operations.
11 December 2019 TDC-1782-005 74
Intelis Gas Meter Installation Guide 6 Adjusting the Calibration