Installation Guide
Table Of Contents
- Contents
- Important Safety and Compliance Information
- USA, FCC Part 15 spectrum compliance
- Canada, ISED spectrum compliance
- RF Exposure (FCC/ISED)
- Australia, ACMA spectrum compliance
- Electromagnetic compatibility
- Intrinsic safety
- Lithium battery
- Transportation classification
- Electrostatic discharge
- Electrostatic ignition hazard
- Device cleaning
- Do not drop
- Product notification
- Intelis Gas Meter
- Installing the Intelis Gas Meter
- Intelis Gas Meter LCD Operation
- Proving the Intelis Gas Meter
- Adjusting the Intelis Gas Meter Calibration
- Intelis Gas Meter Index Replacement
4. From the Operate Valves and Observe Sensor Readings screen, press the 1 key or
Chuck V
alve to clamp the meter in place.
5. After the Intelis Gas Meter is clamped to the prover, turn on the appropriate nozzle in the
center of the screen to exercise the meter
.
Note: Nozzle 6-250 is typically used for the Intelis Gas Meter.
Exercise the meter for 10 to 15 minutes before proving the meter.
6.
Close the nozzle.
7. Unclamp the meter by pressing the Chuck Valve button.
8. Exit Operate Valves and Observe Sensor Readings.
Setting up the Measurement Systems prover
1. Open the MMS prover application.
2. Select Meter Setup Menu.
Proving the Intelis Gas Meter