Installation Guide
Table Of Contents
- CCU 100 and Repeater 100 Installation Guide
- Important Safety and Compliance Information
- 1 Before You Begin
- 2 CCU/Repeater Basics
- 3 Planning a CCU/Repeater Installation
- 4 Installing the Collector or Repeater
- 5 Battery Care and Maintenance
- A Detailed Collector or Repeater Specifications
- B Port and Protocol Requirements
- C Status and Diagnostics
- D Changing the Repeater Password
- E Antenna Line Sweeps Procedure
- Anritsu Site Master Calibration
- Testing on a Network Device with a Remotely-Mounted 915 MHz Antenna
- Understanding Party Responsibilities
- Itron ChoiceConnect Antenna and Line Sweep Test Form
- Itron ChoiceConnect 915 MHz Antenna Specifications
- Typical Coaxial Cable Specification Summary Table
- Sample Sweeps Output
- F Grounding Specifications
- Understanding Grounding and Bonding
- Exterior Grounding System Design for Concentrators
- Equipment Buried Ground Ring
- Chemical Ground Rod Installation
- Itron Concentrator Equipment
- Installing Coax Ground Kits
- Collector Sites with Indoor Itron TCU / CCU Equipment
- Grounding Rooftop Network Devices
- Down Conductor Installation
- Cold Water Pipe Option
- Building Steel Option
- Antenna and Coax Grounding - Rooftops
- Grounding antennas on rooftops
- Cable Tray Grounding
- Water Tower Grounding
- New Wooden and Concrete Antenna Poles
- Equipment Shelter Grounding
- Repeaters on Communication Tower Sites
- Repeaters on Rooftops
- Multiple Story Site Ground System
- Down Conductors Installation - Building / Shelter Penetrations
- Down Conductors Installation - Limits of Bend Radius
- Down Conductors Installation Connection Methods
- Cable Entrance Facilities
- Clamp-On Ground Resistance Testing
- Understanding Party Responsibilities
2. Attach the 4G WAN antenna on the N-Connector on the bottom of the CCU labeled WAN.
Battery
If you are installing a battery with a ferrite bead on the wires, as shown in the following
illustration, follow the directions in Installing the Battery (Ferrite Bead) on page 50.
If the battery does not have a ferrite bead on the wires, see Installing the Battery on page 49.
Installing the Battery
1. Remove the battery cover by loosening the four screws securing it.
These are captive screws. It is not necessary to fully remove the screws from the battery
cover.
2. Plug in the four pin battery wiring harness. The harness should snap into place, providing a
secure connection.
23 June 2020 TDC-0971-012 Itron, Inc. Page 49 of 134
CCU 100 and Repeater 100 Installation Guide 4 Installing the Collector or Repeater