User's Manual
Table Of Contents
- Before You Begin
- CCU/Repeater Basics
- Planning a CCU/Repeater Installation
- Installing the Collector or Repeater
- Installation Overview
- Attaching the Local GPS/WAN Antennas
- Attaching the Direct Mount Standard (5.15 dBi) 900 MHz Antenna
- Attaching the Collector or Repeater
- Connecting Cables
- Installing a Local 4G WAN Antenna
- Installing the Battery
- Providing Power
- CCU Installation Wiring Diagram
- Tower Installation
- Solar Powered Installation
- Relocating a CCU or Repeater
- Battery Care and Maintenance
- Detailed Collector or Repeater Specifications
- Port and Protocol Requirements
- Status and Diagnostics
- Changing the Repeater Password
- Antenna Line Sweeps Procedure
- Anritsu Site Master Calibration
- Testing on a Network Device with a Remotely-Mounted 900 MHz Antenna
- Understanding Party Responsibilities
- Itron ChoiceConnect Antenna and Line Sweep Test Form
- Itron ChoiceConnect 900 MHz Antenna Specifications
- Typical Coaxial Cable Specification Summary Table
- Sample Sweeps Output
- Grounding Specifications
- Understanding Grounding and Bonding
- Understanding the Ohms Level
- Reducing the Ohms level
- Using a Megger
- Adjusting the Routing of the Grounding Conductor
- Supplier General Requirements and Equipment Competencies
- Exterior Grounding System Design for Concentrators
- Equipment Buried Ground Ring
- Chemical Ground Rod Installation
- Itron Concentrator Equipment
- Installing Coax Ground Kits
- Collector Sites with Indoor Itron TCU / CCU Equipment
- Grounding Rooftop Network Devices
- Down Conductor Installation
- Cold Water Pipe Option
- Building Steel Option
- Antenna and Coax Grounding - Rooftops
- Cable Tray Grounding
- Water Tower Grounding
- New Wooden and Concrete Antenna Poles
- Equipment Shelter Grounding
- Repeaters on Communication Tower Sites
- Repeaters on Rooftops
- Multiple Story Site Ground System
- Down Conductors Installation - Building / Shelter Penetrations
- Down Conductors Installation - Limits of Bend Radius
- Down Conductors Installation Connection Methods
- Cable Entrance Facilities
- Clamp-On Ground Resistance Testing
- Understanding Party Responsibilities
- Understanding Grounding and Bonding
- Index
Chapter 3 Installing the Collector or Repeater
28 TDC-0971-011 CCU 100 and Repeater 100 Installation Guide
Proprietary and Confidential
Davit Arm Mount
The following figure illustrates a typical utility pole or street light pole installation. The
collector or repeater is mounted on a davit arm or the street light arm. Two types of power
connections are typical. You may use a photocell adapter cable when the collector or
repeater is mounted on a street light arm. This cable plugs into the photocell sensor of the
street light. Use of the photocell adapter requires the collector or repeater be grounded
using the grounding lug on the bottom of the collector or repeater. If the collector or
repeater is mounted on a davit arm with no street light, the power cable must be connected
according to local electrical codes.
To mount the collector or repeater on a davit arm
1. Using the two mounting brackets and four bolts, attach the mounting plate to the davit
arm.