User's Manual

Installing the 100W and 100WP ERT Module
TDC-0909-004 100W and 100WP Datalogging ERT Module Installation Guide 14
Proprietary and Confidential
Required Tools and Hardware
Hammer
1/2-inch outside diameter rod (you may use either a square or round rod)
Tape measure
Rod-driving tool (optional)
Rod cutting tool
The 1/2-inch diameter rod hole is shown in the following 100W and 100WP ERT module bottom and side
views.
To install the 100W and 100WP ERT module on a rod
1. Remove the pit lid. Inspect the area to make sure there are no buried cables, pipes, or other obstructions.
2. Measure the pit box depth from the top of the lip (where the lid will rest) to the bottom of the pit. Be sure
to measure the depth at the point where you will drive the rod into the ground.
3. Add 12 inches to the pit box depth measurement taken in step 2. The resulting total represents the
minimum length of rod needed. Soil types and moisture conditions may require longer rod lengths to
ensure the ERT module is well supported and remains vertical.