Installing the 100W Endpoint
TDC-0909-002 100W and 100WP Pit Datalogging Water Endpoint Installation Guide 23
Proprietary and Confidential
5. Verify the clip locks into place in the housing.
Caution Carefully align the 100W through lid assembly. If the assembly is improperly aligned, the pit lid
may not close.
Pit Lid Mounting Kit installation is complete.
Installing the Endpoint in a New Lid
This section describes installation of the 100W endpoint in a pit lid without a drilled hole.
To install the 100W in new lids
1. Select a hole location with enough clearance on the bottom side of the lid to attach the threaded clip collar.
2. Drill a 1-3/4 inch hole in the lid.
3. See To install in lids with holes using the Pit Lid Mounting Kit on page 21 to complete installation in a
new lid.