User's Manual
Table Of Contents
Connecting the 100T-CP Module to the Test Station
TDC
-1344-000 100T-CP Cathodic Protection Telemetry Module Installation Guide 12
Proprietary and Confidential
7. Perform a Check Endpoint using a handheld computer and FDM to display the pipe to soil and AC
voltage readings measured by the 100T-CP.
8. A negative DC voltage indicates a successful connection. If the Check Endpoint indicates a positive DC
voltage, switch the red and black lightning suppressor leads on the test station terminals.
9. Perform a Check Endpoint to verify a negative DC voltage.
Warning Allow one minute between readings for the voltage to stabilize.
Programming the 100T-CP
Caution You must program the 100T-CP before use.
Program the 100T-CP using an FC200SR or FC300 handheld computer loaded with FDM Endpoint Tools.
For complete programming information, see the Field Deployment Manager Endpoint Tools Mobile
Application Guide (TDC-0934).
Program the Utility ID into the 100T-CP using the handheld computer. Optionally, you can program the
100T-CP to enable the enhanced security key, Test Station ID, and voltage reading Capture Hour. For all
programming and Check Endpoint operations, hold the handheld within six feet of the target telemetry
module and as close to vertical as possible. Programming parameters are based on the configuration file
loaded into the programming device.