User's Manual
Itron/Sprague Meter Installation
TDC-0823-005 100G Datalogging Installation Guide - Direct Mount 29
Proprietary and Confidential
2. Loosen the index mounting screws 1/2 to one turn. Slide the index to the left and off the mounting screws
and remove from the meter.
Set the index aside where it will not be damaged or fill with dirt, rain or snow. The index is mounted in
the endpoint later in this procedure. Verify the index mounting screws are 1/4" long and not corroded. If
the screws are the correct length and not corroded, retain for later use. If the original screws are discarded,
use the correct replacement screws (see Installation Prerequisites on page 7).
3. Remove the old gasket, gasket residue, and dirt from the meter (if applicable). The meter face must be free
of gasket residue or dirt before you install the 100G Datalogging gas endpoint.
To assemble the 100G Datalogging gas endpoint and index
1. Separate the 100G Datalogging gas endpoint housing from the cover by pulling the cover straight out from
the housing. Set the endpoint cover aside where it will not be damaged or fill with rain, dirt or snow. You
will use the cover later in this installation procedure.