User Guide
The Station Test Run feature enables all stations to be automatical-
ly operated in sequence using a temporary run time from 1 to 10
minutes. Perfect for a quick check of the system after installation or
service.
1. Place the Function switch in the Run position.
2. Turn the Dial to the Skip Days/ Special Functions position.
4. Press the Manual button one time to move from the initial
Skip Day screen to the Station Test screen.
3. Use the and buttons to set the desired run time.
5. Press the Semi-Auto button to start the watering cycle.
6. Turn the Dial to the Current Time position.
Note: Once started, the station sequence can be manually
advanced by pressing the Manual button.
Station Test Run Feature
15
Equipment Ground
to Green
Hot to Black
Neutral to White
1/2" (13 mm)
Conduit Body
Figure 7
Figure 8
Key