2021 IRONRIDGE, INC. VERSION 3.1 FLUSH MOUNT INSTALLATION MANUAL - 13
TILE
Remove tile and mark rafter. Position base over rafter, 
adjust arm if necessary and torque hardware to 132 in-lbs 
(11 ft-lbs). Use base as guide to drill 1/4" pilot holes, back 
ll with roong manufacturer’s approved sealant, then 
insert lag bolts and tighten until fully seated. Replace tiles 
and notch as necessary to ensure proper t. Attach rails to 
either side of slot using Bonding Hardware and torque to 
250 in-lbs (21-ft-lbs). 
 ➢ Position arm near the center of valley for curved tiles.
 ➢ Position arm away from seam of joining at tiles.
 ➢ Ensure top of hook does not extend above rail. 
 ➢ Standalone All Tile Hook manual available on website.
Rafter
Torque to 
132 in-lbs
Torque to 
250 in-lbs
Tighten Until
 Fully Seated
Remove tile and mark rafter, use Base Plate to mark two 
holes on rafter. Drill two 7/32" pilot holes and back ll 
with roong manufacturers' approved sealant. Use 1/2" 
socket to drive lag into place. Slide hook into place and 
adjust to desired position. Drive self-tapping screw using 
a #3 Phillips bit to lock hook in place. Clean underlayment 
and apply a bead of sealant compatible with roong 
manufacturer, install ashing over mount. Fasten sub-
ashing to deck with one roong nail in each corner. 
Waterproof at underlayment level according to roong 
manufacturers' instructions and the Tile Roong Industry 
Alliance guidelines. Cut clearance notch in the weather 
guard of tile as needed or utilize QMPV Tile Replacement 
Flashings. Attach rails to either side of slot using Bonding 
Hardware and torque to 250 in-lbs (21-ft-lbs). 
 ➢ Position arm near the center of valley for curved tiles.
 ➢ Position arm away from seam of joining at tiles.
 ➢ Ensure top of hook does not extend above rail. 
 ➢ For additional details refer to the full QMPV Installation Manual. 
QMPV QUICK HOOK
ALL TILE HOOK