Post Installation Checklist
The following table lists the tasks that should be performed upon completing installation.
TABLE 4: POST INSTALLATION CHECKLIST
NO. CHECKLIST ITEM
;
1 Scope out the entire area setup to locate any obvious problem areas.
2 Check antenna routing for safety concerns and near-field boundary setup.
3
Use tie wraps, where possible to ensure that all cables routed in parallel are
bundled together.
4 Perform appropriate testing to ensure base station works properly.
Once installation is complete, make sure the area is clear of debris that would prevent proper
airflow and ventilation.
No transmitter tuning or adjustments are to be performed in the field. The base station is
factory set to meet all FCC requirements as required by the base station certification.