User's Manual

SECTION 4: PRODUCT INSTALLATION
637246.DOC Page 18
Post Installation Checklist
The following table lists the tasks that should be performed upon completing installation.
TABLE 5: POST INSTALLATION CHECKLIST
NO. CHECKLIST ITEM
;
1 Scope out the entire area setup to locate any obvious problem areas.
2 Check antenna routing for safety concerns and near-field boundary setup.
3
Use tie wraps, where possible to ensure that all cables routed in parallel are
bundled together.
4 Perform appropriate testing to ensure base station works properly.
Once installation is complete make sure the area is clear of debris that would prevent proper
airflow and ventilation.