User's Manual

© ip.access Ltd
COMPANY CONFIDENTIAL 110#010XA_GDE.doc
- 14 -
2
Locking Spring
1
TOP
Figure 7 Mounting the nanoBTS
b) Fixing to a ceiling or a sloping surface
When fixing to a ceiling or a sloping wall the same fixing process and clearances should be
observed as for fixing to a wall (at least 80mm from the bracket to the top of wall and
120mm from the side of the bracket to a side wall). On a sloping surface the top of the
bracket
MUST
be uppermost. Once the unit has been attached to the bracket the outer
cover
MUST
be removed to expose the cooling vanes.
Preparation for configuring nanoBTS
Connect the nanoBTS as per figure 3, to either a 48volt wall socket or to the nanoBTS side
of a PSU.
Check the power on self-test sequence by observing the Status Indicator on the nanoBTS.
The normal sequence is described below,
a) Red shows briefly.
b) Orange glows continuously for around 45 seconds as unit boots up.
c) If the boot process is successful the Status Indicator shows orange with a slow
blink (Off – 0.1 seconds. On – 1.9 seconds).
NOTE:
Do not connect the nanoBTS to the LAN until the DHCP server is running on the
configuring PC. This is especially important if there is already a DHCP server running on
the LAN
Repeat for all other nanoBTS before proceeding to the configuration.