When fixing to a ceiling or a sloping wall the same fixing process and clearances should be
observed as for fixing to a wall (at least 100mm from the bracket to the top of wall and
120mm from the side of the bracket to a side wall). On a sloping surface the top of the
bracket MUST be uppermost. Once the unit has been attached to the bracket the outer
cover MUST be removed to expose the cooling vanes, as shown in Figure 15.
Figure 15 - Ceiling mounted nanoBTS
2.5.7 Mounting Multi-TRX nanoBTS
When the nanoBTS are to be installed in a Multi-TRX configuration, then each TRX should
be installed in a similar orientation but not closer than 30cm to each other.
A further specific constraint is that the TIB cables must be <1.5m and a 1.5mm
2
Chassis
Bond cable must also be connected between each TRX with a length not exceeding that of
the TIB cable.