User's Manual

nanoLTE AP Hardware Installation Installation Overview and Requirements
NANO_INST_43311 v101_0.2 for N4G_1.1 © ip.access Limited 2016 Page 2
2 Installation Overview and Requirements
2.1 Installation Tasks
The tasks that must be completed to install a nanoLTE AP and make it ready to provide
service are:
Pre-Provisioning
Site installation
These tasks can be completed in any order. In most cases, however, the most practical
approach is to pre-provision an AP before site installation. The procedures for these
activities are provided in the AP Configuration Manual [INST_43370].
2.1.1 Pre-Provisioning
For information about AP pre-provisioning, see the AP Configuration Manual [INST_43370].
This manual has no further information on AP configuration.
2.1.2 On Site Installation
Physical installation of a nanoLTE AP at its operating site, including providing the AP with
power and a suitable network connection that provides a backhaul path to the NOS Server
and EPC.
If a nanoLTE AP has been enabled for service prior to the site visit, the installation engineer
can make test calls immediately.
Note: Due to the physical installation requirements of a nanoLTE AP, which must be securely wall
mounted in a location with adequate ventilation, it is recommended that an E40 AP is
installed by a suitably qualified site installation engineer.