User's Guide
Table Of Contents
- nano3G AP Installation Manual
- Table of Contents
- 1 Introduction
- 2 Installation Overview and Requirements
- 2.1 Installation Tasks
- 2.2 Requirements for All nano3G APs
- 2.2.1 General Requirements
- 2.2.2 nano3G AP Cooling
- 2.2.3 Information Required for Pre-Provisioning
- 2.2.4 Parameters for Enterprise Deployments
- 2.2.5 Parameters for Residential Deployments
- 2.2.6 Access Control
- 2.2.7 Closed Access with CSG Parameter Broadcast
- 2.2.8 Closed Access in Legacy Mode
- 2.2.9 Pre-Prepared Configurations - Optional
- 2.2.10 Information Required for Commissioning
- 2.2.11 Other Items for Commissioning
- 2.3 nano3G S8 AP Site Requirements
- 2.4 nano3G S16 AP Site Requirements
- 2.5 nano3G E8 AP and nano3G E16 AP Site Requirements
- 3 Pre-Provisioning a nano3G AP
- 4 Configuration File Preparation
- 5 Commission a nano3G AP
- 6 nano3G AP Hardware Installation
- 7 Finalize Installation
- 8 Troubleshooting
- 9 nano3G AP and PSU Regulatory Information
nano3G AP Installation Manual Commission a nano3G AP
N3G_INST_300 v292_1.0 for N3G_2.92 © ip.access Limited 2012 Page 57
5.5.2 Configure the NOS Server Connection
27) If a secure connection is required, select IPSec Enabled. Also enter the address
for the IPSec Gateway and the Traffic Selector address and subnet mask.
28) Enter addresses for the NOS Server (Management Server URL), a suitable CRL
server and the NTP server.
The settings applied on this page are retained permanently as the default set of
these parameters, and can only be subsequently changed on this web page from a
commissioning terminal.
Note: The NTP and CRL servers must be accessible to the AP on start up,
before it has established an IPsec tunnel to the Security Gateway.
29) To save the configuration, click Apply Changes.
Note: At this point it may be useful to make a separate note of the parameter
values entered in this screen. Alternatively, save a screenshot of the web
page (information about how to take a screenshot is outside the scope of
this manual).
5.5.3 Complete the AP Commissioning
30) Click the Connection Config link on the left, to ensure the correct page is
showing.
31) To start the AP in normal operation mode, click Complete Commissioning.
32) Acknowledge the warning about changes in the IP configuration and click OK.
33) When the initial configuration is complete, power off the AP and disconnect it from
the commissioning terminal.