Installation Instructions

WiBAS / WiBAS G5 Base Stations
Installation & Cabling Manual - Edition 3.2
257
Power Supply
Introduction
Apply this procedure for terminating the following power supply cables:
AC cable AC-PWR-CAB (3 x 0.75 mm
2
) for PONE-OD67-AC and POE-
HP-OD-AC.
DC cables DC-PWR-CAB-1 (2 x 1 mm
2
) for POE-HP-OD67-DC and DC-
PWR-CAB-3 (2 x 2.5 mm
2
) for WiBAS
TM
G5 dual-BS.
For DC cable termination ((DC-PWR-CAB-2 (2 x 2.5 mm
2
)) of PONE-
OD-DC refer to Procedure on page 236.
For DC cables termination of the following power injectors refer to item
6 of Reference manuals on page 14:
IDU-O4P (indoor)
IDU-O10P (indoor)
OmniBAS
TM
4W/8W IDU (indoor)
Termination
overview
The pictures below shows a termination overview of power supply cable to
the respective connector:
Tools and
materials
Tools
Blade, cable cutter, soldering iron, solder (refer to Termination
of cables).
Materials
AC-PWR-CAB
DC-PWR-CAB-1 or DC-PWR-CAB-3
PONE-OD67-AC
POE-HP-OD67-DC
Continued on next page