Users Manual

WiBAS OSDR-Hub & Terminal Station / WiBAS-Connect Terminal Station
Start Up & Commissioning Manual - Edition 5.1
79
WiBAS-Connect TS (Auto-Polarization Edition), Continued
Procedure for WiBAS-Connect Auto-Polarization TS with Parabolic Low Profile Antenna,
continued
Step
Action
7 The commissioner should compare the captured values from steps 4 and 6.
If t
he horizontal value is better than vertical then perform the steps 9 and 10.
If the vertical value (captured on step 4) is better than horizontal then procced to
the next step.
8 Perform the following actions:
Remove the RSSI cable from TS and after 2-3 seconds inserted again (as
described to
RSSI cable connection procedure on page 42).
Wait 30 seconds. During boot process the voltmeter shows ~2.5 V.
Please do not perform any action till the boot process of the TS is completed.
After boot process the TS starts automatic process scan (vertical), and:
S/W selects F1 frequency (in horizontal polarization) and requires 10 seconds to
provide the QI value on the voltmeter.
S/W selects F2 frequency (in horizontal polarization) and requires 10 seconds to
provide the QI value on the voltmeter.
For QI values please refer to QI table on page 93.
Verify on the voltmeter the QI value is maintained as previous captured on step 4.
9 Permanently remove the RSSI cable and install the protection cover.
Continued on next page